Study of a Bridge Project at La Boule
Commissioned by: The Société du Pont sur le Saguenay, a non-profit organization representing the citizens of the Côte-Nord region.

The authors
- Pierre Brisset, retired architect and author of the 1986 Study
- Buckland & Taylor/COWI, expert engineers in the construction of long suspension bridges. They supervised the construction of the Izmit bridge in Turkey, the 3rd longest suspension bridge in the world, opened in June 2016. They are completing the supervision of the construction of the Hålogaland Bridge at Narvik (Norway), whose opening is planned for 2017.
The structure
A suspension bridge with a main span of 1,150 m, 2 lanes and a deck 15 metres wide. The proposed structure is very similar to that of the Narvik bridge, nearing completion. Moreover, in 1986 and 1998 this lower bridge project, with a 2-lane deck, had already been proposed. This bridge has undergone the most rigorous tests and meets, thanks to new technologies, the new European standards, including a 200-year lifespan. (See G1 to G26)
Main observations
After 30 years of involvement in the Tadoussac bridge project, the now-retired architect Pierre Brisset compiled and studied the results of the earlier studies and again proposed a bridge at La Boule (P1), respecting the recommendations of the experts and avoiding a tunnel on the south shore, since the mountainside allows an ascent at an MTQ-standard grade of about 6%. A 600-metre tunnel is necessary on the north shore to pass under the La Boule mountain. This tunnel should not prevent the passage of vehicles carrying hazardous materials. Since the 1960s, on the Trans-Canada Highway in British Columbia, one can pass through several tunnels, including a 750-metre tunnel, the China Bar, in which all traffic is permitted.
The bridge site at La Boule has several advantages:
- Being located upstream of the Hydro-Québec power lines, its visual impact on the estuary is limited.
- It gives access on the north shore to the main community of the Saguenay estuary: Sacré-Cœur-sur-le-Fjord, a particularly dynamic community of about 2,000 inhabitants (G32 to G35).
- It facilitates road links between the three villages of the estuary: the village of Baie-Sainte-Catherine (200 inhabitants), Tadoussac (800 inhabitants) and Sacré-Cœur-sur-le-Fjord.
The international expert firm COWI, which knows the region well from having proposed a bridge project there in 1999, confirmed the feasibility of the bridge project and the costs. (English version: G1 to G13 and French version (translation) G14 to G18)
Considering the confusion and all the biases that have surrounded the earlier studies, it appears desirable that a technical study be commissioned from an independent firm with recognized expertise. This will allow decision-makers to have an accurate picture of the costs of the project at La Boule. After 43 years of contradictory studies and counter-studies, after decades of resistance by senior MTQ officials to the realization of the project — even though all the independent studies on the costs of the crossing compared to the costs of a bridge confirm that it is more advantageous to use public funds to build a bridge than to maintain a ferry service in the estuary (G36, G37) — it is time that an independent, complete and objective analysis of the construction and maintenance costs of a bridge compared to the total costs of the ferry service at Tadoussac be ordered.
The attached documents (letter from Pierre Brisset, COWI’s response and cost summary were sent to the Québec Minister of Transport on May 30, 2016 (G1 to G18, G37, G38)).
Existing examples, a price to be specified

The Hardanger Bridge, Norway
The Hardanger Bridge, like the Narvik bridge, cost about C$250M (2015). The costs of a bridge at Tadoussac lie between C$250M and C$300M. So the time of contradictory studies should come to an end. All that remains is to specify the prices of the bridge and of the approach roads to the La Boule site. It will thus be possible to measure the extent of the public funds that will be saved by reallocating these funds, and the extent of the funds saved that could be reallocated to other projects, including the completion of Route 138 on the Lower North Shore. The Confederation Bridge, in Prince Edward Island, was financed in large part by the reallocation of the funds used for the Borden–Cape Tormentine ferry.
The optimal alignment
The selected site makes it possible to join Route 138 at Baie-Sainte-Catherine or to consider the completion of an expressway in the Charlevoix hinterland, which would free up the coastal road for tourism purposes and mitigate the harm to road safety when passing through the villages. The right-of-way already largely exists. Thus, heavy vehicles and regular (non-tourist) users could travel from the top of the hill at the western exit of the town of Clermont to the intersection of the new bridge road and Route 138, near the intersection of Route 172 and Route 138. This fast route would avoid the substandard grades and curves of Route 138 as well as the passage of tractor-trailers through the heart of the villages. The distance to be travelled would be similar to the current coastal route on Route 138 between the intersection of Routes 172 and 138 and the top of the hill on Route 138 at the western exit of the town of Clermont, i.e. about 80 kilometres in both cases. (G29 to G31).
The Société du Pont, faced with the finding that the 1999 and 2009 studies presented approach-road projects to the La Boule site (P1) with costs inflated by 6.5 kilometres of tunnels in 1999 ($483M (1999)) (G8) and 5.45 kilometres of viaduct in 2009 ($353M (2004)) (F46), reviewed the earlier alignments and presents a road project at more acceptable costs (G46 to G50), similar to the costs of a 2-lane road presented by the MTQ in the LGL 1979A study (A13) and in the update of the prices of this road by the MTQ engineers in 1995 (D3):
- By eliminating most of the tunnels and long-span viaducts that are not necessary.
- By eliminating the concept of a 4-lane highway in a mountainous region, knowing that Route 138 is a 2-lane national highway and not a freeway. The Société proposes a 3-lane road in which the 3rd lane will be a passing lane on uphill grades.
- By partially using existing rights-of-way, namely the Chemin des Loisirs in Baie-Sainte-Catherine on the south shore and the Rang Saint-Joseph in Sacré-Cœur-sur-le-Fjord on the north shore. These two roads have already led to the La Boule site (P1) for several years.
In presenting this project at La Boule, the Société du Pont is inventing nothing and does not claim to take the place of the experts, but rather to convey a more intimate knowledge of the terrain and the environment.
Sabotage of the Tadoussac bridge project by senior MTQ officials
The determination of senior MTQ officials to harm the project for more than 40 years has forced us to present a realistic option at an affordable cost which is, essentially, an update of studies 1979A and 1986 and of certain work carried out by MTQ engineers. We have become aware that this opposition of senior MTQ officials to the project is not shared by all MTQ staff. The great majority of professionals have shown exemplary cooperation. However, when in 2001, at the very start of the 2009 study, the ministry’s senior management chose to transfer the director and deputy director of the Côte-Nord territorial office — both engineers who had stated in the project notice for the impact study that the ferry service had reached its limits and that it was now necessary to move forward with the construction of a bridge — we understood that economic, technical or environmental considerations were not the cause of this attitude (F2 to F6). We then chose to carry out this analysis of the studies and to propose to the Minister of Transport an objective and independent update of the bridge project by recognized experts in this particular field of long suspension bridges. The use of parameters that vary according to the location of a project is not justifiable. (For example the discount rates, which vary threefold depending on whether the project is wanted or not by who knows whom:
- 1973: 2.7% MTQ, C. Hamelin, engineer (I4)
- 1999: 8% Naturam/Génivar consortium, Tadoussac bridge (E12)
- 2009: 5% SNC-Lavalin/Génivar consortium, Tadoussac bridge (F7.15, F7.16)
- 2011: 3.3% Transport Canada, MTQ, BCDE consortium, Champlain Bridge (F54)
- 2015: 2.6% Transport Canada, SSL consortium, Champlain Bridge (G44, G45)
The impact of these rates on a project can be measured in appendix (F7.16)
When the Société du Pont attempted to approach the Minister of Transport to explain the anomalies in the studies that had been identified as originating from the STQ or the MTQ’s territorial divisions, he refused twice to meet us and redirected us to a senior official of the Côte-Nord territorial office who had taken part in the latest studies (F55, F56). We had already met this person several times to ask questions. Recently again, after submitting new questions, we received answers nearly a year later — answers which, in several cases, amounted to inviting us to contact other entities under the responsibility of the Minister of Transport, or, in one case, allowed us to become aware, more than 10 years late, of an important document (Appendix, Addendum P1) (F64 to F67). Yet the Société du Pont was represented on the Advisory Committee on the Impact Study from 2001 to 2009, and we never received a copy of this addendum. Moreover, by redirecting us once again to the Société des Traversiers (STQ), we were being sent into a dead end: indeed, the STQ has in the past refused to answer our questions on the pretext that they required analytical work that the law did not oblige them to do. (K14, K15)

The culture at the Ministry of Transport of manipulating information, omitting key information, and significantly overestimating and underestimating alternative projects according to the Ministry’s wishes (see press clippings on price inflation at the MTQ (F57, F58), the LRT and the AMT, an agency under the responsibility of the Minister of Transport (E24), like the Société des Traversiers du Québec (F59 to F63)) leads us to believe that the political world is not what dictates the orientations and decisions of senior officials at the MTQ. Another world is at work, and a careful reading of this analysis of the studies on the Saguenay crossing on Route 138 will allow interested persons to penetrate a counter-culture that has obeyed the law of silence for decades (B2). Committees for demolishing structuring and profitable projects are nothing new at the Ministry of Transport. As volunteer citizens in the project and as taxpayers, this counter-culture worries us because it leads to erroneous political decisions, the socio-economic stagnation of at least one region of Québec, the squandering of public funds and, above all, it perverts the exercise of a healthy democracy.
For more detail:
- the important appendices cited above: Click here