Impact Study of the Project to Build a Bridge over the Saguenay River
Municipalities of Tadoussac and Baie-Sainte-Catherine, RCMs of La Haute-Côte-Nord and Charlevoix-Est

Important observations
The complete impact study can be viewed on the site here (SNC-Lavalin/Génivar study)
Commissioned by: the Québec Minister of Transport, at a cost of $2M (2002)
The authors
- The SNC-Lavalin/Génivar consortium and the Ministry of Transport
- Parsons Brinckerhoff Quade & Douglas, Inc., Engineers
Several participants from Génivar and the Ministry of Transport took part in the 1999 opportunity study and took part in the 2009 study. However, the international experts in long suspension bridge construction who prepared the bridge project of the 1999 study were not retained.
The structure and the proposed alignment
The bridge proposed on alignment P4, near the ferries, has a main span of 1,350 metres and a total span of 2,010 metres. It will have a downward slope of 2.1% from the south shore to the north shore. The height of the deck above the water will be 140 metres at the south-shore pylon and 112 metres at the north-shore pylon. The great height of the deck is the consequence of the elimination of the tunnel planned in the 1999 study on the south shore. Finally, the deck will have 4 lanes and a carriageway width of 25 metres. (F29, G24).
Comparison of existing bridges and bridge projects at Tadoussac

On the technical level

- The Ministry of Transport favours, as in the 1999 opportunity study, the alignment of study 1979B that a Ministry urban planner had prioritized, despite the opinion of the Montréal and New York engineers of study 1979A.
- Whereas the 1999 study proposes: a suspension bridge with a main span of 1,420 metres, a total span of 1,740 metres, 4 lanes, a 1.2 km tunnel to the south and a 950-metre viaduct to the north of the river, for a project of about 4 km of structures plus the approach roads (E9) — these 3 structures extend over 4 kilometres
- This 2009 study proposes: a suspension bridge with a main span of 1,350 metres and a total span of 2,010 metres, and a 900-metre viaduct on the north shore, for a total of nearly 3 km for the 2 structures plus the approach roads. The tunnel on the south shore is eliminated at the price of a raised deck and a 2.1% slope. These two structures extend over 3 kilometres
- The international experts in long suspension bridges Buckland and Taylor made a recommendation in 1999 to the effect that the price of the bridge could be substantially reduced if the height of the deck were lowered from 88 metres to meet international navigation standards, which are rather around 70 metres (E13). In this study, the Ministry of Transport, by requiring the removal of the tunnel, forced the deck to be raised from the 88 m proposed in 1999 to 140 m in 2009 at the south pier. This decision largely explains the inflation of the cost of the bridge project, making it a pharaonic structure. The price of the bridge itself would be raised from $253M (1999) to $712M (2004), i.e., when adjusted to 2015 dollars, an increase in 5 years of more than $500M. (Study 1999: $345M (2015) vs Study 2009: $860M (2015)).
- Moreover, such a structure requires a 10-year period for preparation and construction. Similar bridges, at normal height, elsewhere in the world require 4 years of construction (See Hålogaland bridge or Hardanger bridge).
The bridge at the optimal location of La Boule
Study of alignment P1, Addendum 1 to the 2009 impact study (Appendices F41 to F47)

At the request of the architect Brisset, in 2004, the MTQ asked the SNC-Lavalin-Génivar consortium to assess the costs of a bridge at the optimal site of La Boule, upstream of the power lines. (E38, E40)
This information was not made public, and therefore the Advisory Committee on the impact study, in which the Société du Pont sur le Saguenay participated, was not informed of the existence of this Addendum 1, even though the architect Pierre Brisset had requested this update of the La Boule bridge project from the MTQ by letter as early as 2004.
In August 2016, following our request made verbally during a formal meeting with the MTQ’s Côte-Nord territorial authorities on September 2, 2015, and transmitted by letter in March 2016, the Ministry sent us this document.
On the technical level, therefore, the SNC-Lavalin/Génivar consortium’s cost estimates for the bridges at La Boule (P1) or near the ferries (P4) are inflated, considering that the price of the bridge assessed in 1999 by the long-suspension-bridge experts Buckland and Taylor/COWI put the bridge at P4 at $345M (2015), whereas the consortium assesses a similar bridge at the same site, with a main span reduced by 70 metres, at $860M (2015).
The cost of the approach roads is also very high and difficult to justify. In 1999, the MTQ and the Naturam-Génivar consortium estimated that 6.5 km of tunnels would have to be built on the approach roads to P1, at a cost of $660M (2015). 5 years later, the MTQ and the SNC-Lavalin/Génivar consortium consider that tunnels are not necessary on this road, and they are replaced by highway viaducts at a cost of $428M (2015). Moreover, Route 138 is a 2-lane national highway, so nothing justifies a 4-lane highway to reach the bridge at P1; a 2-lane road with a third passing lane on uphill grades would suffice.
Finally, 2 access roads to site P1 already exist, and a drive along the alignment proposed in the 2015 study showed us that it is possible to build a 3-lane national road without multiplying kilometres of infrastructure such as viaducts or tunnels.
On the socio-economic and environmental level
The study on these aspects was conducted by several of the participants who prepared the 1999 Opportunity Study. The spirit of the study is therefore similar.
Absence of an independent and complete analysis of the costs of the ferry service and of the trend of these costs relative to inflation and to the evolution of traffic.
An abnormal importance is again given, as in the 1999 study, to the traffic trend, whereas the project notice (appendix F2 to F6) points out that the ferry service is saturated during the periods of heaviest traffic, throughout the year. Attempting to define a traffic trend on a road that is saturated and whose dangerousness and unpredictable travel times are recognized as deterrents is illogical. It reflects an urban vision of roads without taking into account that the limiting factor on this road is not the road but the boat the user must take to continue the trip. This misunderstanding by urban specialists leads us into a vicious circle originating from this misunderstanding, which can be pictured as follows: “The more the ferries deter use of the road, the more traffic plateaus or declines, and the more traffic plateaus or declines, the less a bridge is justified.”
The only important questions are:
- What are the total costs of the crossing, its administrative expenses and its onshore facilities?
- What are the total costs of the bridge and its approach roads that are not village bypasses?
- What are the indirect costs of the ferries (ferry syndrome, time lost, unpredictable travel times, economic effects, various disruptions)?
The Norwegians did this exercise in the case of the Hardanger fjord crossing, a crossing every 20 minutes over a distance of about 1.6 km with traffic 20% lower than that of the Tadoussac crossing. They concluded that a bridge is more cost-effective and built the Hardanger Bridge between 2009 and 2013 at a cost of C$250M (2013)
As a sub-question:
- What are the foreseeable costs of the road works that will be necessary to relieve congestion in the villages of Baie-Sainte-Catherine and Tadoussac, and of those that will also be necessary to upgrade Route 138 in terms of passing zones in order to reach the provincial average of 60% and thus hope to dissolve the platoons of 115 car-equivalents that will regularly exit the large ferries proposed by the STQ?
This study presents several anomalies, all of which result in a bias in favour of maintaining the ferries. In fact, no independent study is available to us to assess the true costs of the ferry service. Dozens of pages of the study deal with traffic forecasting. Route 138 near the ferries is saturated by the ferry service itself. While the road can carry up to 25,000 vehicles per day, the ferries are the limiting factor, with a maximum capacity of around 5,000 vehicles per day. Their variable schedules and the numerous disruptions that make travel time unpredictable have the effect of deterring use of the road and thus limiting the growth of its traffic as well as the growth and diversification of the economy of the Côte-Nord region and of the regions with which it trades. Hence the authors’ insistence on giving disproportionate importance to traffic fluctuations on a saturated and deterrent road, which prevents regional businesses from delivering or receiving their products according to the “just in time” standard; this breach of trust caused by the unpredictability of the crossing makes our businesses more fragile and less competitive. The regional economy is thus limited to the extraction and shipping, mainly by sea, of raw materials. This saturation also prevents the emergence of a flourishing tourism industry all along the Coast.
The cost-benefit analysis
A dangerous and costly weapon for Québec taxpayers if used by the holders of knowledge against regions that have no university or academics able to provide access to knowledge, and which are therefore subject to a biased interpretation of their realities, or even to non-rigorous analyses that distort reality. (See: comparison of the rates for the Champlain Bridge versus those for the Tadoussac bridge in point 4 of the socio-economic observations of the 1999 study)
The cost-benefit analysis is one element among others of an impact study and is the result of the use of several parameters to assess whether or not a project is worth carrying out. However, the Ministry of Transport used this highly subjective instrument to guess the future. In March 2006, during the presentation of the preliminary version of the impact study, the result of this analysis was made public and presented to the national media to explain that this bridge project was not profitable for “Québec society”.
Yet, after analysis, we find that several errors, omissions and choices distorted the result of this analysis and almost all aimed to discredit the bridge project.
- The price of the bridge project, 2 times higher than the project presented 5 years earlier in the 1999 Study by the Buckland and Taylor experts (F29). For the bridge alone, the cost of the bridge near the ferries at P4 is $253M (1999) (E5), whereas the SNC-Lavalin/Génivar consortium proposes at the same site (alignment P4) a bridge costing $712M (2004).
- In the 2015 study, the Buckland and Taylor/COWI engineers propose on alignment P1, at La Boule, a bridge costing $275M (2015) (G13). The bridge proposed by the SNC-Lavalin/Génivar consortium at the same site P1 at La Boule would cost $712M (2004) or $860M (2015), i.e. more than 3 times the price presented by COWI in 2015. (F11)
- The total costs of the ferry service at Tadoussac were underestimated. Moreover, whereas in August 2009, at the time of publication of the final version of the Impact Study, the Société des Traversiers estimated that the current ferries (Armand Imbeault and Jos Deschênes) had a useful life until 2025, the Société des Traversiers and the Minister of Transport announced 3 weeks later, in September 2009, the construction of two larger ferries to replace the two current ferries prematurely and without acceptable justification (K2, K3) as early as 2013. No planning, preparation or consultation relating to this decision other than a meeting at the Premier’s office and a sudden decision on the premise that a bridge would cost $1 billion and that the Davie shipyard wanted to build boats to avoid bankruptcy. (K43, K44)
- The Société des Traversiers proposed a reconstruction cost for each of the ferries of $27M (2004), then the Consortium re-evaluated it at $35M in 2006, then, after the intervention of the Société du Pont, the MTQ re-evaluated it at $42M in 2009 (F25), and finally, to date, these ferries will cost over $100M per ferry including the redevelopment of the access ramps. These costs could rise further, since the delivery date is still not confirmed and there is already a delivery delay of more than 3 years. Financing costs will therefore also increase as a result of construction delays. Other “extras” are therefore also to be expected. (K83, K84)
Parameters with variable geometry
- The study’s discount rate: This is the rate of preference for the present and therefore aims to assign a value to a project according to the importance one is willing to give today to its value in the future. In other words, if a bridge has a lifespan of 200 years, how many generations should pay for this bridge? The higher the rate, the more the current generation pays. The longer the infrastructure’s lifespan, the lower the discount rate should be. Likewise, the shorter the project’s lifespan, the higher the rate: roads, for example, which have a lifespan of 30 years, will not have the same discount rate as a bridge whose lifespan is estimated at 125 or 200 years. This rate is an important determinant of the cost-benefit analysis. In 1999, the reference rate retained in the cost-benefit analysis was 8%; in the present study it was set at 6% and then 5% (F21). Yet after some research, we found that the discount rate recognized by Transport Québec, the federal government and the engineers of the BCDE consortium for the Champlain Bridge construction project in 2011 was 3.3% (F54), which is close to the discount rate of 2.7% suggested by an MTQ engineer in the 1974 study (F53).
- For information, if the discount rate of 3.3% (Champlain Bridge) had been used, the cost-benefit analysis of the pharaonic SNC-Lavalin/Génivar project would have produced a positive NPV (Net Present Value) of more than $100M (2004) rather than a negative one of $89M as in the analysis of the final version of the study. (F8, F9) A road can have a lifespan of 30 years, a bridge more than a hundred years, and a ferry about 40 years, provided a major modernization with re-engining is carried out after 20 years. The bridge over the Saguenay proposed at the optimal site at La Boule would have a lifespan of 200 years if satisfactory maintenance is maintained (G13). The new Champlain Bridge would have a lifespan of 125 years. So the Tadoussac bridge, whose piers are on dry land and not exposed to ice, salt and other agents, should theoretically benefit from a lower discount rate than the Champlain Bridge. Paradoxically, the 5% rate retained penalized the Tadoussac bridge project, even with the high costs then proposed, whereas the 3.3% rate facilitated the completion of the Champlain Bridge. For example, if the same rate as that used for the Champlain Bridge in 2011 had been used, the cost-benefit analysis of the 2009 impact study would have been positive by about $100M (2006). This variability of the proposed rate could be one of the “variable geometry” parameters used by the MTQ to encourage or discourage the feasibility of a project. This exercise in fortune-telling is in fact highly subjective and subject to manipulation of all kinds depending on the result desired by the party commissioning the “study makers”. (F71 to F73)
- Modernization, also called mid-life refit, was omitted from the impact study even though its cost is significant. Thus, the modernization of the current vessels (Armand Imbeault and Jos Deschênes), built in 1980 at a cost of $5M each, took place in 1997. This modernization was combined with an enlargement of 15 car-equivalents (from 60 to 75 car-eq.), at a cost of $14M (1997) per ferry (F52). The omission of this information is not trivial in the calculation of the future costs of the ferries and biases the cost-benefit analysis.
- Road safety influences the cost-benefit analysis and therefore a decision to carry out or not carry out a project. Accidents resulting from the ferry syndrome are monetized by the experts. Yet the MTQ estimated in the preliminary version of the impact study that the life of a person killed on Route 138 between La Malbaie and Les Escoumins should be worth $3.6M according to the WTP (willingness to pay) method, whereas a study on the conversion of Route 175 into a highway estimated that the life of users was worth $5M per death. After some research, we found that the expert recognized by the Québec Ministry of Transport in matters of cost-benefit analysis is precisely one of the authors of the 1970 Higgins Martin Raynauld (HMR) study, which recommended that the Québec government stop investing in regions far from the centre unless these investments generated substantial revenues for the centre, and centralize structuring government investments in the metropolis. (F49, F50, F71 to F73)) This sum of coincidences led us to question the parameters used in cost-benefit analyses and their variability depending on whether the project is metropolitan or in regions far from the metropolis. If it were established that the culture of the Ministry of Transport is anti-regional and pursues the spirit of that 1970 study (HMR), said to have been decisive in the establishment of the “Québec model”, there would be reason to question the true intentions of the Québec government concerning the retention of Quebecers to occupy the territories of the remote regions. Perhaps the government ultimately wishes to close the region and maintain only extraction sites there. If so, this would contradict the very spirit of the Plan Nord. Another explanation could be an anti-regional culture within the MTQ unbeknownst to the political actors; this approach could explain the remarks of the Deputy Minister at the MTQ, recently ousted and promoted to the Premier’s office, to the effect “that she takes no orders from the minister”. Finally, in our effort to try to understand all these biases, another plausible explanation could have been to protect the jobs of MTQ officials or of the Société des Traversiers du Québec, itself under the authority of the Minister of Transport.
Whatever the explanation, it does not fit with the political message conveyed by the promoters of the Plan Nord, nor with the mission of the Ministry of Transport (which is to facilitate the movement of people and goods between the regions of Québec). Moreover, the Premier of Québec has acknowledged the existence of this counter-culture at the Québec Ministry of Transport (K33 to K37)
After the MTQ made public the broad outlines of the preliminary version of the Impact Study in March 2006, one could hear on Québec’s national networks that this pharaonic bridge project was not desirable for Québec and that it entailed a loss over 40 years of 233 million dollars (1999) (F57 to F60). In the following months, after reading this massive document of more than a thousand pages, the Société du Pont intervened with the Ministry to point out several anomalies, oversights or errors (F15 to F28). After lengthy discussions and a trip to Québec City to obtain the assent of the Assistant Deputy Minister responsible for eastern Québec, the ministry corrected certain anomalies partially or totally. A process that continued from March 2006 to October 2007. However, in the absence of expertise on the Côte-Nord on all the technical aspects of the proposed project, none of these questions was addressed at that time. They would be in the years 2014-2016, after an expert agreed to join the Société du Pont’s analysts to review the technical aspects of the study.
Biased information

An article published in 2006 in a local newspaper (F48) is representative of the message conveyed to all the media following the Ministry of Transport’s information session on the preliminary version of the 2009 Study. The information conveyed requires a few corrections and additional comments on the points identified in this article. Please enlarge the image below to identify each of the points:
- The study was 2 years behind schedule in 2006; it would be delayed until August 2009, thus becoming obsolete and impossible to present to the National Assembly. Indeed, a rule provides that any study not completed within 5 years of its start is considered outdated and therefore inadmissible. The MTQ shelved the study for nearly 5 years, since it was originally to be made public in 2004, i.e. 2 years after its start.
- A shortfall of $233M (2004) to be expected. Without even considering the price of the bridge, 3 times higher than the optimal option at P1, and the price of the ferries divided by 3 compared to the real costs known to date according to the price provided by the Société des Traversiers in 2004, $27M (2004) vs $100M and more (2015) (F25). After the Société du Pont sur le Saguenay notified the MTQ of these biases, some of them were mitigated or corrected, and the theoretical shortfall went from -$233M to -$89M. Recall that no analysis of the technical aspect of the study had then been made by the Société du Pont’s analysts, for lack of available expertise. (F15 to F28)
- The 3 factors that, according to the study, could influence its result are:
- “Higher demand”: How can higher demand be obtained on a saturated road whose travel times are unpredictable and whose dangerousness and unpredictability, linked to numerous disruptions, deter its use?
- “Greater consideration for long-term benefits”: Why does a bridge planned for 100 years in Montréal have a discount rate of 3.3%, reflecting the duration of its value over time, whereas the same rate at Tadoussac is arbitrarily set at 5%? Double standards? (At 3.3%, the result of the cost-benefit analysis goes from -$89M (2004) to +$100M (2004)) (See appendix F7.16)
- “The construction period of the project”: 4 years, based on similar bridges built with new technologies, rather than 9 years.
- “The bridge would not be the 5th longest suspension bridge”: if the bridge were built at the location recognized as optimal since 1979, at La Boule, with a main span of 1,150 metres as proposed in the 1979, 1986 and 2015 studies, it would be between the 30th and 40th longest suspension bridge in the world depending on its commissioning date. The idea here is not to break a record but to cross a river.
- The cost of the bridge, as explained above, is clearly overestimated.
- “7 years of construction”, whereas similar bridges are now built in 4 years. This parameter significantly changes the final result of the analysis, since the 9 years assessed by SNC-Lavalin/Génivar mean that for the first 9 years of the analysis the benefits of the bridge are not counted, since the ferries must remain in operation.
- “The contribution of public funding would remain very considerable even when spread over a long period.” The reality, if the numerous biases and omissions are corrected, is that the reallocation of the public funds needed to operate the Tadoussac crossing to the financing of a bridge will free up substantial and annually growing sums that would otherwise have to be applied to the ferry service. And after 40 years, a bridge would remain available for another 160 years if well maintained, incurring only annual maintenance costs, which are minimal compared to the operating costs of the ferries (crew salaries, fuel, maintenance and administrative costs, upgrading and rebuilding of equipment and onshore facilities including the wharves). And these ferries have zero value after 40 years and must be modernized after 20 years.
- The final version of the study was to be submitted in the spring of 2006; it would finally be submitted at the end of summer 2009. Asking regional people, unfamiliar with this type of study of more than a thousand pages, to review the study in one month is not realistic
- “The Minister will base his decision on the results of the study.” When officials present decision-makers with documents they have helped to bias or from which they have excluded important information, the resulting political decisions are not the right ones; they are costly for all Quebecers and alienating for the Plan Nord region and for the Québec economy.
The letter sent by the Société du Pont to the MTQ in March 2016 concerning the assessment of the approach roads to alignment P1 at La Boule referred to the plans prepared by the MTQ engineers in 1979 as part of LGL’s Study 1979A (A13). The costs of the approach roads to La Boule (P1) were re-evaluated by the MTQ engineers in 1995 (D3). Following our request, the MTQ was unable to provide us with the detailed plans of these approach roads. These plans would have been of interest in assessing the alignment then retained, which seemed much less costly than those presented in 1999 and 2009 — one with $483M (1999) of 4-lane highway tunnels on a 4-lane highway and the other with $353M (2004) of 4-lane highway viaducts on a 4-lane highway. In 2005, the approach roads to bridge P1 at the place known as La Boule were around $540M (2015) (F47), whereas in 1999 these same roads were assessed at $738M (2015) (E5); very high prices considering the MTQ’s earlier assessments of 1979 and 1995 of $65M (2015) (A13, D3) and those estimated in Study 2015 of $125M (2015) including a 600-metre tunnel.
All the information concerning the Impact Study is available on the site here, with the exception of Addendum 1 concerning the cost assessment on alignment P1, a copy of which is in appendix F41 to F47.
As well as:
- the important appendices cited above: Click here
- the complete study