Study 1999

Opportunity Study on the Crossing of the Saguenay River between Baie-Sainte-Catherine and Tadoussac

Appendix EA

Simulation de pont

Commissioned by: the Québec Minister of Transport

*complete study at the bottom of the page

The authors

  • The Naturam-Génivar consortium and the Québec Ministry of Transport (MTQ), whose team included the author of the 1995 study. Naturam is an SME from Baie-Comeau specializing in the environment, while Génivar is a Montréal consulting engineering firm. The study was directed by a co-owner of Naturam, and the project manager was a Montréal urban planner, like the one who directed the internal 1979B study prepared by the MTQ.
  • Buckland and Taylor (COWI) Ltd, Bridge Engineering: This firm, with offices in Canada, is internationally recognized for its expertise in the construction of long suspension bridges. At this very moment, they are completing the supervision of the construction of 2 bridges of interest: the Izmit bridge in Turkey, opened in June 2016, the 3rd longest suspension bridge in the world, and the Hålogaland Bridge at Narvik in Norway, which is at the cutting edge of new technologies and makes it possible to build a 3-lane deck for a 1,150-metre bridge. We will return to this Narvik bridge in the 2015B study.

Structure

The experts and the MTQ propose a project extending over 4 kilometres, consisting to the south of a 1.2 km tunnel followed by the suspension bridge with a total span of 1,740 m and a 950 m viaduct (E4, E5, E14, E15). The project alignment is similar to that proposed in study 1979B, prepared in the MTQ’s internal study (B5). The cost of the complete project including access roads amounts to $371M (1999), while the cost of the suspension bridge amounts to $253M (1999)

Main observations on the technical level

See the correspondence and summary analysis of the architect Pierre Brisset, who had already been interested in the Tadoussac bridge file for nearly twenty years. (E28 to E41)

The earlier studies of 1979A and 1986 recommended building a bridge at La Boule, upstream of the Hydro-Québec power lines, i.e. on alignment P1 (E4)

Yet the MTQ had this choice contradicted in study 1979B by proposing instead a bridge near the ferries, i.e. alignment P4 (E4), even though the engineers had previously ruled out this alignment as too costly.

The MTQ overestimates the cost of the approach roads by incorporating, without justification, 6.5 kilometres of tunnel on a 4-lane road joining a 4-lane highway bridge. These tunnels are unjustified.

In addition, a calculation error overestimates the bridge at La Boule by $60M (1999). Indeed, the price of the bridge of option P3, with a main span of 1,360 metres, at $234M (1999), was confused with the bridge of option P1, which has a main span of 1,150 metres.

The price of the bridge for the optimal option should have read $174M (1999) (See appendix E5)

E4 mapetude1999

Through these two anomalies, the cost of the bridge at P1 was inflated by 300%, i.e. more than $500M (1999)

Following these results, the optimal option at La Boule was set aside. The MTQ and the consortium sent the B&T/COWI experts documents to prepare and evaluate a bridge project near the ferries. These documents included 3 earlier studies (E3), namely:

  1. the one that the MTQ made on the quiet in 1979 (1979B), in which, against the advice of the engineers, the MTQ decided to present a project near the ferries, on very rugged terrain — terrain that would require the construction of 4 kilometres of massive infrastructure (E9) — and the 2 studies prepared by the engineers of
  2. LGL (1979A) and
  3. the Brisset et al. study (1986), which recommend a bridge at the La Boule site.

Among these documents, the Ministry asked B&T/COWI to prepare a bridge project on 3 alignments (P3, P4, P5) (E3), knowing that alignments P3 and P5 were unfeasible, P3 being on steep terrain impassable at an affordable cost and P5 requiring passage through the very heart of the village of Tadoussac. The price of the project on the optimal alignment P1 was therefore inflated by unjustified tunnels, a 4-lane highway on a 2-lane national road, and a calculation error. (E7)

The B&T/COWI engineers present an affordable bridge project ($253M (1999) (E46 to E48) within an overall 4 km-long project at $371M (1999), namely: a 1.2 km tunnel, a 1,760-metre bridge and a 950-metre viaduct. The 2009 impact study would eliminate the tunnel on the south shore at the MTQ’s request, present a shorter suspension bridge (1,350 m main span instead of 1,420 in the present study (Option P4 of appendix E5)), and yet would raise the cost of the bridge alone from $253M (1999) (appendix E5 option P4) to $712M (2004) (F11), even though the 2009 bridge option has a main span reduced by 70 metres (1,350 m versus 1,420 m in 1999).

The MTQ and Génivar engineers required COWI to prepare a bridge project with a deck located 88 metres above the water. This requirement generated high costs, and B&T/COWI, in its report, would make a clear recommendation:

“The lowering of the vertical profile should be viewed as a strong opportunity to reduce the crossing costs since the 88 metre height of deck above water appears excessive in comparison to typical navigational clearances prescribed elsewhere” (E13)

f29

The height of the deck is excessive, and yet, in the 2009 impact study, the MTQ would require the SNC-Lavalin/Génivar consortium to eliminate the 1.2 km tunnel on the south shore and therefore to raise the bridge deck above the mountain, to a height of 140 metres, thereby driving up the price of the bridge. (F29)

The study confuses the length of the bridge on alignment P1 at La Boule and its cost with that of alignment P3. For P1, a bridge with a main span of 1,150 metres is indicated at a cost of $218M (1999), whereas on page 220 (E15) for P1 a bridge with a main span of 1,220 metres is presented, and on page 219 a bridge cost of $234M is indicated (E5). Finally, the bridge at P3, with a main span of 1,360 metres, is presented at a cost of $234M (1999). Using the parameters used for the costs of the other alignments, a corrected cost for P1 of $174M (1999) is obtained (E6). In the 1998 study the MTQ assessed the cost of the bridge at P1 on axis D at $218M (1998), and in 1999 the 1,150-metre bridge (Option DD) was assessed at $115M, an amount adjusted for inflation in the 1999 study to… $218M (1999) (E7, E8).

Main observations on the socio-economic and environmental levels

A cost-benefit analysis is presented (E12) in which several shortcomings are noted.

  1. It does not include the capital costs of the ferries
  2. It does not include the costs of the mid-life refits that the ferries must undergo after 20 years of operation,
  3. The entire cost of the bridge is charged in the first year, whereas it will be built progressively over 4 or 5 years.
  4. It is indicated that the discount rate used will be 5% (E18), whereas in the reference scenario a rate of 8% is used (E12). These rates are abnormally flexible, especially when one knows that they apply in constant dollars, i.e. inflation is excluded from this parameter:

1973: 2.7% (I4), MTQ, letter from the engineer C. Hamelin.

1999: 8% (E12) Naturam/Génivar consortium, Tadoussac bridge

2009: 5% (F7.15, F7.16) SNC-Lavalin/Génivar consortium, Tadoussac bridge

2011: 3.3% (F54) Transport Canada, MTQ, BCDE consortium, Champlain Bridge

2015: 2.6% (G44, G45) Transport Canada, SSL consortium, Champlain Bridge

Note in appendix F7.16 the impact that this single parameter can have on the result of the cost-benefit analysis, namely the Net Present Value (NPV).

  1. Road safety is not considered an issue (E17). The costs related to road safety are therefore eliminated (E10, E17); it is considered that the number and severity of accidents are not an issue at the Tadoussac crossing — which the coroner Dr. Arnaud Samson would contradict in 2001 by describing the “ferry syndrome” and identifying the number of deaths, serious injuries and accidents occurring on the approach roads to the crossing. (See Ferry syndrome, Dr. Arnaud Samson.) Moreover, in November 2005, the researchers of the program JE on the TVA network showed that Route 138 between Québec City and Sept-Îles is the deadliest road in Québec and that the approach sectors to the ferries are particularly dangerous. The MTQ would acknowledge in the 2009 study that 30% of the deaths, injuries and accidents occurring on the approach roads to the ferries can be attributed to the crossing itself.

Urban paradigms to be rethought for projects outside cities

mathematics-1509559_640

Several paradigms used by urban planners and urban economists do not apply in the regions. If we stuck to these paradigms, only Montréal would remain as an inhabited centre in the province. Indeed, the relevance of a road is assessed by the population it serves rather than by the need to access Québec’s territory. Thus, where there are a million people, all projects are permitted and encouraged according to the parameters used in this study. Conversely, if 100,000 people maintain economic activity on a territory as vast as Norway, it is not justified, according to the proposed parameters, to maintain or complete a road serving it and to encourage its development. This historical approach of repulsion towards our own territory could explain the cession of the Labrador territory to the neighbouring province and the disintegration of all the regions that are not on the periphery of the metropolis. Here are a few paradigms that should be revisited.

Paradigm 1

Opening up the region will be useless

mapQC

In this study, as in that of 2009, the authors refuse to consider the benefits of opening up the region for the regional economy: tourism, the processing of raw materials, the retention of existing businesses and the establishment of new ones, on the pretext that only time lost has economic value. The urban planner (a word whose Latin origin means one who is concerned with the city) in charge of the project considers that the issue at Tadoussac must be viewed in the same way as a Montréal traffic issue: consequently, the spin-offs of a bridge and the opening up of the region must not be considered. A review of the spin-offs of the opening of the Laviolette Bridge at Trois-Rivières nevertheless clearly demonstrates the bridge effect, as does the opening of the Pierre-Laporte Bridge, among others. Fluid and safe road access is an unavoidable premise for the diversification of a regional economy and its development. What would the Montréal economy be if dozens of bridges had not been built to reach the island? The study refuses to consider this obvious fact (E17).

Yet for decades, the importance of opening up isolated regions has been recognized internationally.

The meaning of “désenclavement” (opening up) was defined by the French geographer Jean Labasse as: “the coherent attempts undertaken by public authorities to break the material and moral isolation of areas otherwise doomed to economic stagnation or political secession.” L’Organisation de l’Espace. Paris, Herman, 1966.

In a remote environment, when a single national highway serves a region whose territory is equivalent to that of Norway, when this road is the only national highway serving eastern Canada — the Côte-Nord and Labrador, a territory as vast as France — when this road ends in a dead end at both its extremities, Tadoussac and Kegaska, completing this road with a bridge and opening the territory towards the east represents a major and decisive economic impact for the future of the region and for Québec. A Québec that for decades has neglected its primary market, where it could have a decisive influence, forgets what makes a great nation: its capacity to exchange and trade around itself. This obvious fact was not perceptible to the urban planners, possibly because there is no centre of higher learning or university in the Côte-Nord region to convey these realities. Moreover, despite their lack of knowledge of the North Shore environment, the expertise of urban planners and economists from the centre is sought. Recall that according to a survey, 70% of Quebecers have never been to the Côte-Nord. (Léger Marketing survey commissioned by the CRÉ Côte-Nord in 2005)

Paradigm 2

Putting all one’s eggs in the same basket

(Higgins, Martin, Raynauld study 1970)

oeufs

Urban experts trained in metropolitan or American universities promote the American model of territorial development. This is a model in which large cities of more than a million inhabitants, for example, concentrate economic activity while the surrounding regions supply consumers and goods to the central city. In the USA, this model applies fairly well, since urban centres of more than a million people are spread over the entire territory, thus creating natural competition between them and generally bringing the regions closer to the central cities. In Québec, the application of this American model is a mistake. Since the 1970s, attempts have been made to apply this model to Québec, and the results are alarming. The great distances between the regions and the off-centre core in the extreme south-west of the territory make this model a destroyer of wealth. By persisting in applying it, the government accentuates the disintegration of its peripheral regions and weakens its centre. In 1970, Montréal was considered the Canadian metropolis. Since then, the Québec model has integrated the suggestions of the economists Higgins, Martin and Raynauld to concentrate structuring investments in the metropolis and its surroundings. As a corollary, they proposed limiting structuring investments in the regions and restricting them to industrial investments — meaning profitable for the centre. Montréal was to become an economic locomotive to which the regions would hasten to attach themselves as soon as it left the station.

In reality, it must be acknowledged that, for 40 years, the locomotive has never left the station and that the carriages of the peripheral regions have deteriorated for lack of the investments necessary to ensure at least their maintenance. Montréal, meanwhile, has lost its status as the Canadian metropolis to become a provincial city around which more than 90% of Quebecers cluster on a thin strip of territory.

A look at the top of the organization chart of the Ministry of Transport shows the omnipresence of Montréal (E24) in the senior positions of the Ministry.

If today the political community asserts that this concentration of investments from the early versions of the Québec model is no longer applied, the Ministry’s organization chart seems to have remained frozen in time and to apply the precepts of the HMR 70 study to the letter. One of the authors of that study is, moreover, an expert to whom the MTQ refers in matters of cost-benefit analysis (F49, F50, F71 to F73). As it happens, in light of the weaknesses, pitfalls and abuses in the cost-benefit analyses of this study and of the 2009 study, one may be surprised that the Ministry uses as a reference document a work by this author entitled: Weaknesses, Pitfalls and Abuses in Cost-Benefit Analyses (Université de Montréal, 1993) (F73). Are the numerous biases identified to sabotage the bridge project linked to the manipulators of knowledge?

On such a trajectory, destructuring its territory, Québec might have to accept the change or disappearance of its territory, which could be ceded to the peoples who have historically used it. These peoples, through the royalties on the resources they would harvest, would be in a position to maintain its occupation and develop it.

The cost-benefit analysis

Parameters with variable geometry

digital-marketing-1563467_640

Our observations indicate that the parameters used in these analyses are very “flexible” depending on whether a project concerns the centre or the regions (Discount rate: Champlain Bridge 2011 at 3.3% versus the discount rate in the 2009 impact study of 5% (F54)). Among other inappropriate parameters, one may note the value of human life, the exclusion of economic impacts, the analysis of regional projects on the basis of traffic trends without considering the limits due to the saturation of the ferry service or the importance of the territory to be served. As it happens, the Côte-Nord is a spearhead of the Plan Nord, and the only national highway available to reach it imposes a ferry service at the very entrance to the region (E49). On the Côte-Nord, merely maintaining the condition of the existing roads is a constant challenge. The MTQ considers that building a bridge to cross the Saguenay River could prevent the maintenance and improvement of Route 138 (D3), whereas the reallocation of the funds currently paid to the Société des Traversiers would precisely free up funds to improve and complete Route 138.

A destructuring Québec model

By applying this North American approach to Québec, geographical realities were ignored. Québec is isolated in the extreme north-east of the continent; a single major city, Montréal, after decades of centralizing policies, has accumulated most of the province’s wealth, and consequently the basket in which all our eggs were placed has sprung a leak, and a not insignificant part of the collective wealth is no doubt still being lost into the hands of groups pursuing their own interests, as the Charbonneau Commission partly demonstrated.

The Québec model and air transport: the same alienating model

This North American model is also the one applied in the field of air transport with the hub-and-spoke system, whereby travellers from the regions must report to a central airport before being able to take an international flight. In Québec, the population centre is located in the anti-centre that is the extreme south-west of the province, making the American-style service model all the more unsuitable, creating captive markets on which the national carrier has, since the late 1980s, imposed high fares to enable it to be more competitive on international routes. The Québec government soon wishes to organize another symposium on competition and fares in air transport to Québec’s peripheral regions. Air transport is under federal jurisdiction, and Montréal will not allow pressure to be put on the national carrier so that it leaves regions that have been bled dry in terms of service for lack of reasonable fares. The sword of Damocles permanently hanging over the city’s head for decades — the threat of the national carrier’s head office leaving for Toronto — prevents the Québec government from fostering the emergence of competitive carriers dedicated to regional customers.

The only proposal acceptable to the Québec government would once again be to reassure the national carrier by guaranteeing the retention of its captive markets through the injection of taxpayers’ money to finance it, thereby encouraging it to perpetuate the current alienating model. The state already invests public funds for travel originating, among other places, from the Lower North Shore. By encouraging the absence of competition, the government creates a lose-lose-lose situation for passengers and the captive customers of the regions, and a win-win situation for the national carrier. The most disadvantaged people of the remote regions, who must fly out of necessity (to receive medical care, educate their children, train the workforce), are made to pay in order to offer better prices to the better-off of the centre who wish to take holidays in the south. This way of subsidizing the national carrier accentuates inequalities within the Québec population. (E44)

The air transport example applies well to this attitude of the MTQ regarding road development: do everything to avoid investments in the regions except to favour profitable industrial projects, such as a road to a diamond mine, for example. Yet the human desertification of Québec’s territory and its maintenance as a zone of extraction sites and shipping of raw materials, without real access to the processing of our resources, harms all Quebecers, including those of the centre. (see the site: www.aviationregionalequebec.com)

Paradigm 3

The traffic trend is decisive

Road traffic is the main factor that can determine when a bridge should be built, according to the authors (E22). The use of this paradigm by the MTQ distorts reality. The road has been saturated by the presence of the ferries for more than 40 years (see studies 1973 and 1976). How then can one hope for an increase in traffic?

The figures show that traffic on Route 138 is limited by the unpredictable and often dangerous conditions to which the ferries subject road users. This limitation or saturation, even more evident in summer, creates a vicious circle in which the region is condemned to stagnate. It is the inverted logic of the sausage advertisement: the more saturated the ferries, the less traffic growth there will be, and the less growth there is, the less there will be a bridge.

Yet what matters is to know the true total costs of the ferries at Tadoussac and of the facilities supporting them on shore and in the capital, and to compare these with the true total costs of the bridge and its approaches, considering the benefits and drawbacks of this opening up.

Bridge or Ferries?

pont-vs-traversiers

That is the only relevant question; using the traffic trend of a road that is saturated and limited by the ferry service itself is illogical.

As long as a functional road link is not completed, fluctuations in raw material prices will also have a direct effect on road traffic.

In 1973, the engineer Monti did the exercise and showed that a bridge was more advantageous than maintaining the ferries. In 2015, the Société du Pont sur le Saguenay reached the same conclusion (See Study 2015). After 43 years of spending millions on studies sponsored by the MTQ — studies too often lacking in rigour — it is time to ask experts to assess the costs of this bridge precisely, and it is also time to ask rigorous and competent engineers to establish the costs of the approach roads to the optimal site known for nearly 40 years.

Paradigm 4

The crossing does not prevent travel

The authors trivialize the deterrent effects and the costs to regional industry of the ferries on exchanges between the Côte-Nord and the rest of the continent. (K19 to K23)

Observations on the environmental level

  • The disturbance of the habitats of raptors and cetaceans is mentioned (E18). Yet it is difficult to understand how a bridge would disturb cetaceans more than the ferries operating day and night in the heart of the river estuary, where belugas historically feed (E26). Studies increasingly target the noise of boats as a cause of the disappearance of belugas. Indeed, communication between mother and calf takes place through underwater sound waves, which are scrambled when boats are nearby. The calf can thus lose its mother and die of starvation. If, as the federal government has just announced, belugas are an endangered species, it is important to take measures to protect them, and keeping ferries permanently in the estuary is not one of them.
  • Urban destructuring (E18): Linking the village of Sacré-Cœur, the main community near the Saguenay estuary, to the municipality of Baie-Sainte-Catherine by a bridge will ensure the future of the 3 villages of the estuary and develop a critical mass to better occupy the territory. Currently, a trip between Tadoussac (800 people) and Baie-Sainte-Catherine (200 people) takes about 30 minutes with the ferries. With a bridge at La Boule, this trip will take the same time; moreover, the people of the village of Baie-Sainte-Catherine will have faster access to the economic centre of the estuary: the municipality of Sacré-Cœur-sur-le-Fjord (2,000 people), a community whose dynamism and sense of cooperation and entrepreneurship are well known in the country. Several businesses already belong to the industrial cluster its citizens have created, and the completion of the road with a bridge would allow the community and the region to take off anew.
  • The loss of use of agricultural land (E18): The alignment to La Boule does not cross any farmed agricultural land.
  • The alteration of highly valued natural environments (E18): This alteration, by placing the bridge at La Boule, will be very limited and less than the maintenance of ferries and wharves in the estuary.
  • The disturbance of the landscape (E18): At the La Boule site, the suspension bridge, which will be a light and slender road structure above the fjord, will be a first-class attraction in itself and as an observation site. The bridge would be behind the Hydro-Québec power lines and would have a limited effect on the landscape seen from the estuary (Tadoussac or Baie-Sainte-Catherine).

In summary, the opportunity study was biased at several levels

a5

On the technical level

A- by adding 6.5 km of tunnels at a cost of $483M (1999) or $660M (2015), whereas study 1979A and its 1995 update make no mention of any necessary tunnel, nor does the 2009 impact study, which eliminates all tunnels and proposes viaducts towards the La Boule site (P1).

Why did the MTQ introduce 6.5 km of tunnels on the road to La Boule and accept a 1.2 km tunnel on alignment P4 near the ferries in 1999, only to demand, in the 2009 impact study, the removal of the tunnel and the construction of a pharaonic bridge passing over the mountain on the south shore?

B- by proposing a price for the bridge at La Boule overestimated by $60M, thus disqualifying the optimal option recognized in 2 earlier independent studies (1979A and 1986)

On the socio-economic level

A- By presenting a cost-benefit analysis stripped of several significant elements — including, without being exhaustive, the impacts on the economy of the region and of Québec of opening up the Côte-Nord region, the absence of the costs of the ferries’ mid-life refits after 20 years, the omission of the effects of the ferries on road safety, including the ferry syndrome described by the coroner Dr. Arnaud Samson, the absence or underestimation of the capital costs of the onshore facilities — by proposing discount rates of 5% while applying 8% in the reference scenario, and by investing 100% of the bridge costs in the first year when it is known that disbursements will be spread over several years, the cost-benefit analysis represents neither reality nor a credible forecast. (E10 to E12)

B- The omission of the deterrent effects of the ferries on the free movement of people and goods, the unpredictability and the harm to road safety linked to the numerous disruptions caused by the presence of ferries (K53 to K63) deter not only tourists, but also businesses and Quebecers from dealing with a region whose access is difficult, even perilous. Moreover, businesses wishing to be competitive on continental markets are penalized by the costs related to the crossing, currently estimated at about $100.00 per tractor-trailer trip. Beyond the costs, the unpredictability of travel via the Tadoussac crossing discredits the region’s businesses and can cause breaches of trust and loss of contracts in a modern business environment where “just in time” deliveries are the rule.

On the environmental level

Dramatization of the environmental impacts without consideration for the current environmental impacts of the ferries on the landscape of the estuary with the wharves and boats, on the protection of belugas and other marine mammals, and on the human environment.

In short, quoting the 2nd sentence of the conclusion (E18)

“The crossing, which lies on the axis of Route 138, which runs along the north shore of the St. Lawrence River, is in fact the only road transport link connecting the Côte-Nord region directly to the major centres of Québec, namely Québec City and Montréal. It therefore has strategic importance and first-rate economic value for the Côte-Nord region.”

This statement by the authors favours the option of maintaining the ferries. Yet this study contains no serious analysis of the total costs of the ferries at Tadoussac and thus avoids comparing the bridge solution with that of the ferries.

The following version, which might seem just as biased, would nevertheless be a more accurate description of reality:

“The crossing is not a road transport link but rather a ferry service that crosses the Saguenay River, at variable intervals and depending on the occurrence of numerous disruptions (weather, ice, queues, size of exit platoons, presence of priority vehicles, mechanical breakdowns, staff strikes, accidents, annual refits, etc.), carrying the vehicles waiting at the road dead ends of Baie-Sainte-Catherine and Tadoussac. This interruption of the road causes numerous impairments to traffic flow and road safety which tend, over the years, to deter use of the road and thereby harm the economic development of the region served.”

For more detail: