Feasibility of a Bridge on Axis D of the 1979 LGL Study
Commissioned by: Québec Ministry of Transport
The author
- Louis-Georges Coulombe: engineer, Head of the Design Section, MTQ. The author would also take part in the 1999 and 2009 studies.
The structure
After presenting in the 1999 study a bridge project at La Boule with a steel truss deck and steel piers based on the LGL project of study 1979A, the author revised the costs of a bridge on alignment D (N.B.: the LGL project was designed on alignment DD, later named P1) by replacing the steel truss deck with a steel box-girder deck and the steel piers with high-performance concrete piers, making it possible, thanks to these new technologies, to reduce the costs of the bridge by 25% (L1, L2, L3). The interest of this project is that, in addition to a 4-lane highway bridge with a main span of 1,150 metres, it proposes an alternative for a 2-lane bridge 15 metres wide, a width close to that of another long suspension bridge with a narrow 18-metre deck, the Höga Kusten Bridge in Sweden, opened in 1997. In 2013, on the Hardanger fjord, and in 2017 at Narvik, long suspension bridges 15 metres wide were built on two-lane national roads. The author follows the recommendation of the firm Buckland and Taylor and lowers the bridge deck to 75 metres above the water, complying with the parameters provided by this firm, whose expertise in the construction of long suspension bridges is internationally recognized. Finally, the bridge is also located at La Boule, as the experts have proposed since 1979. To obtain the total cost of the project, we added the cost of the approach road proposed by the engineer Lord in the 1995 analysis.
Main observations
Whereas a bridge at $712M (2004) was proposed in the 2009 study, or approach roads at $540M in the 1999 study, this analysis by the head of design at the Ministry of Transport should have immediately raised obvious questions:
How could the MTQ in 1995 assess the approach roads to La Boule (P1) at $65M (1995) when, 4 years later, the same roads were assessed at $540M (1999), i.e. 8 times more?
It was obvious that the optimal option at La Boule was more advantageous and that a more serious study of the cost of the approach roads was essential in order to make an informed decision.
How, in 2004, could the engineers propose a bridge at $712M (2004) when, 6 years earlier, it was known that a bridge could be built (P1 variant D (H9)) for $218M (1998)? (A14)
Who at the MTQ had the authority to impose on the ministry’s engineers an economically unviable option in both cases?
For more detail:
- the important appendices cited above: Click here