Traffic Evolution, Tadoussac–Baie-Sainte-Catherine Crossing
Commissioned by: Québec Ministry of Transport (MTQ)
The author
- Pierre Lord, engineer; Technical Support Service of the MTQ
Structure
The same as that of the 1979 LGL study, at site P1 (E4) at La Boule. Update of the prices of the access roads and the bridge.
Main observations
- This study updates the prices of the bridge and of the approach roads at La Boule and of the bridge on the DD axis planned by the firm LGL in 1979. They present a price range, of which we use the average. Cost of the bridge: $245M (1995) and roads: $45M (1995) (Appendix D3)
- The author points out that if a bridge is built, it will be to the detriment of the improvements that would be required on Route 138 in the RCMs bordering the Saguenay. (D3) This appears to be a rather wrenching choice for elected officials, when no study has yet been made of the real costs of the Tadoussac crossing and of the onshore facilities necessary for its operation and for the safety of its users on the approach road segments. Yet, since 1973, we have known from the Monti study that the Tadoussac crossing costs Québec taxpayers more annually than the financing and maintenance of a bridge.
- The construction of a bridge is again tied to the anticipated growth of traffic on a road saturated by the ferry service. We are thus sent back into the vicious circle whereby “the less traffic there is on the road, the less chance there is of getting a bridge, even if government cuts and tight management of the ferries mean increased waiting times, increased harm to road safety and traffic flow, etc.” To paraphrase a well-known advertisement: “The fewer sausages you eat, the less fresh they are” — and since the ferry service benefits, in a way, from the deterrent effect it induces among its clientele, this logic, if maintained as it was over the past 40 years, ensures the preservation of a few dozen jobs at the ferries and the stagnation and disintegration of the communities that depend on them.
- One can see the alignment proposed by the MTQ during the LGL79 study (black line) and the alignment proposed by the 2015 study (red line) (D4)
- The MTQ maintains its interventions on the bridge proposed near the ferries in the secret 1979 study, referring to its traffic forecasts. (D5)
- The author emphasizes “the magnitude of the sums involved in the construction of a bridge” but omits to mention the magnitude of the sums involved in the Tadoussac ferry service and the risks and consequences of this crossing for traffic flow and road safety, and its deterrent effect on road users and on the economic development of the east of the country.
For more detail:
- the important appendices cited above: Click here
- the complete study: Click here