Study 1979A: Link across the Saguenay River / connecting Baie-Sainte-Catherine to Tadoussac
Read the complete study (final report, April 1979, 231 pages, 9.7 MB PDF, in French)
Commissioned by: the Québec Minister of Transport.

The authors
- LGL consulting engineers; Montréal
- Steinman, Boynton, Gronquist & Birdsall; Consulting engineers, New York
The structure

The engineers propose a bridge with a main span of 1,150 metres on the DD axis (at the place known as La Boule, upstream of the Hydro-Québec lines) with a steel truss deck like the Pierre-Laporte Bridge. A 4-lane highway bridge with a high deck. (A6, A7, A8, A9, A14)
Main observations
- First study formally commissioned by the Québec Minister of Transport, in 1977.
- Construction over 4 years at a cost of $115M (1979) (A8)
- The study was to determine the optimal option from a technical and economic standpoint. (A2)
- The alignments in the estuary were eliminated and, as the optimal solution, an alignment at La Boule, slightly upstream of the Hydro-Québec power lines, was proposed. It is the location offering the best technical choice at the best cost while minimizing environmental impacts.
- The Ministry of Transport prepared the alignment of the approach roads and assessed their costs (A13), and in 1995 had the cost of the bridge on the DD axis and of the approach roads updated (D3). The cost of the bridge on the D axis was updated in 1998, although this alignment had not been retained by LGL in 1979. (appendices L1, L2, L3)
The study concludes that a bridge can be built at the best cost and with a minimum of negative impacts at La Boule, upstream of the Hydro-Québec lines
For more detail:
- the important appendices cited above (A1 to A14): Click here
- the complete study: Click here (final report, April 1979, 231 pages, 9.7 MB PDF, in French)