The Naturam-Genivar project (1999)

Bridge project proposed by the firm Buckland and Taylor in 1999

member of the Naturam-Genivar consortium, responsible for the opportunity study on the Tadoussac crossing.

Pont de l'étude de 1999
Bridge of the 1999 study
View of the Saguenay Fjord at its mouth, site of the proposed bridge
Elevation drawing of the 1999 study suspension bridge (Buckland & Taylor)

After several studies on the question, including that of the engineer Monti in 1976 and that of Letendre et ass. in 1979, the Québec government commissioned an opportunity study in 1995 from the Naturam-Genivar consortium. This study analyzed several sites for the location of a bridge and assessed the costs. The most economical option was retained, namely an alignment slightly upstream of the current ferry service. The depth of the river at the planned site requires the piers to be built out of the water, at the foot of the rock mountains on either side of the Saguenay. The result is a bridge whose main span would exceed 1,400 m and which would join the group of the 10 longest suspension bridges in the world. This bridge would be the longest suspension bridge in the vast area comprising North America, Central America and South America. The alignment retained requires the construction of a 950 m viaduct on the east side and a 1.2 km tunnel on the west side. This latter constraint could have restricted the passage of trucks carrying hazardous materials and forced them to take a long detour via Ville de Saguenay (Chicoutimi), returning to the Coast via Route 172. It also has a significant influence on the cost of the project, which broke down as follows.

Costs of the bridge proposed by the firm Buckland and Taylor in the study of the Naturam-Genivar consortium (1999)

Élévation des pylônes 1999

Elevation of the pylons, 1999

ItemDescriptionCost (1999)
Bridgetotal length of 1,740 m with a main span of 1,420 m253 000 000 $
Tunnel86 000 000 $
Structure950 m viaduct20 663 000 $
Road12.9 km, 4 lanes10 761 000 $
Total370 674 000 $

The structure of the proposed suspension bridge included a deck with a main span of 1,420 m located 88 m above the river’s highest water level.

In light of new developments since this study, including:

  1. awareness of the harm to the safety of road users near the Saguenay River, notably through the description of the ferry syndrome by Dr. Arnaud Samson, coroner;
  2. growth in the number of vehicles to be carried across higher than forecast; consideration of the Labrador highway initiative, through which the Newfoundland government will complete the Trans-Labrador Highway between Labrador City and Blanc-Sablon at a cost of more than $500M, giving the majority of the 28,000 Labradorians road access to the major centres via Routes 389 and 138, and thus requiring passage through the Tadoussac ferry service.
  3. the announcement and preparation of major projects (hydroelectricity, aluminum smelters, mines, etc.) in the Côte-Nord and Labrador regions involving investments of several billion dollars (about 26 billion already known) (investments on the Côte-Nord and in Labrador).
  4. In November 2001, the Québec government commissioned a complete impact study on the construction of a bridge over the Saguenay River at Tadoussac. This new study, begun in the summer of 2002, is to be completed in the fall of 2004 and should make it possible to gather all the relevant information to begin the hearings before the BAPE (Bureau d’audiences publiques sur l’environnement), the mandatory prelude to the construction of the bridge. A sum of two million dollars was allocated to the SNC-Lavalin/Genivar consortium to carry out the study.

To date, the consortium is at the stage of collecting data on the socio-economic and environmental impacts. On the technical level, the SNC-Lavalin group’s engineering team has already established several parameters for optimizing the project.