The choice of discount rate alone often decides the fate of a project. This calculator takes the official figures of the 2009 study and lets you choose the rate. To understand what is at stake, read “The hidden number that decides the fate of the Tadoussac bridge“; all the studies are on the Studies page.
Do the math yourself: is the bridge profitable?
Here are the official figures of the 2009 impact study (table F.14, reference scenario), year by year, from 2006 to 2046. We change only one thing: the discount rate. Move the slider and watch the verdict change.
Each year: discounted benefits and costs
In millions of dollars. The higher the rate, the smaller distant benefits become, while construction costs (at the start) keep their full weight.
Cumulative balance of the bridge
In millions of dollars. The curve adds up, year after year, discounted benefits minus discounted costs. It dives during construction (lowest point in 2014), climbs back with the ferry savings, then jumps in 2046 with the bridge’s residual value. The figure shown for 2046 is the final balance (net present value) at the chosen rate. When the curve rises above zero, the bridge has brought in more than it cost. The study stops the calculation in 2046; the bridge itself will last more than 100 years.
Show the year-by-year table (with the discount factor)
| Year | Discount factor | Benefits | Costs | Discounted benefits | Discounted costs | Discounted net |
|---|---|---|---|---|---|---|
The discount factor of a year = 1 ÷ (1 + rate)number of years since 2006. Each amount is multiplied by this factor. At 5%, it is 1.000 in 2006, 0.952 in 2007, 0.907 in 2008… and only 0.142 in 2046.
Source: SNC-Lavalin/Genivar consortium (2009), Environmental impact study of the Saguenay River bridge project, appendix F, table F.14 (pp. F8-F9, original document in PDF, in French), reference scenario. Amounts in the study’s constant dollars (2004 base), discounted to 2006. The 2046 benefits include the residual value of the bridge ($532M). At 5%, the calculation reproduces exactly the published result: -$89.5M and a ratio of 0.873. Calculation: Société du Pont sur le Saguenay.