History of the Tadoussac bridge project — “More than a hundred years of history”
Updated: August 2025
Contents — 17 milestones
- 1909 – First official request
- 1926 – Election promise of Edgar Rochette, candidate for the Côte-Nord seat
- 1931 – New promise from the outgoing member and future minister
- 1973-1976 – First formal study for the construction of the bridge
- 1979 – Study requested by the Minister of Transport, followed by an internal study carried out without the Minister’s knowledge
- 1997 – Relaunch of the project
- 1999 – Opportunity study
- 2000 – Regional mobilization
- 2001 – Start of an impact study
- 2009 – Environmental impact study
- 2009 – Decision to acquire new ferries
- 2015 – 2018
- 2018–2019 – Commissioning of the new ferries
- 2017-2020 – Announcements and delays
- 2021-2025 – Enhancement study
- 2025 – Reassessment and the Minister’s statement
- Conclusion
1909 – First official request
Mr. Joseph Bureau, Chief Explorer of Québec (what we might today call the head of territorial development), appointed in 1882 by Curé Labelle, then Deputy Minister of Colonization, asked the Minister of Natural Resources in writing to build a bridge at Tadoussac to carry a railway line that would reach the Labrador Sea and the Strait of Belle Isle. Québec would thus gain access to the vast resources of the Côte-Nord region, which at the time included Labrador. Nothing came of it. The province of Québec’s neglect of the North Shore territory led to the cession of Labrador to the Dominion of Newfoundland in 1929 by an order of the Privy Council of King George V in London.
1926 – Election promise of Edgar Rochette, candidate for the Côte-Nord seat
In 1926, Mr. Donat Bouchard, a native of Les Éboulements and at the time a campaign worker for the Côte-Nord candidate, the lawyer Edgar Rochette, reported that the flagship promise of the election campaign was the construction of a bridge at Tadoussac.
1931 – New promise from the outgoing member and future minister

In 1931, the member for Côte-Nord, Edgar Rochette, reiterated his promise to build the Tadoussac bridge. Recall that at the time, the Côte-Nord riding stretched from Saint-Tite-des-Caps in Charlevoix to Blanc-Sablon. During the same election campaign, Premier Taschereau promised a bridge to link Île d’Orléans to the north shore of the St. Lawrence, in the riding of Montmorency. Construction of the Île d’Orléans bridge began in 1933 and was completed in 1935 at a cost of 3.5 million dollars (1935), or $80M (2025). Recall that construction of the Golden Gate suspension bridge in San Francisco began in January 1933 and was completed in May 1937. It had a main span of 1.28 km and a width of 27 m for 6 traffic lanes. The Tadoussac bridge project would be consigned to oblivion, which today appears to be a historic mistake.
The use of election promises in the Tadoussac bridge file is not new and continues today. We will celebrate 100 years of political efforts in 2026.
1973-1976 – First formal study for the construction of the bridge
The British firm Freeman Fox, renowned for having designed in 1970 the first suspension bridge over the Bosphorus in Istanbul (main span > 1 km), joined forces with Monti Coulombe of Montréal to assess the feasibility of a bridge over the Saguenay estuary at Tadoussac.
In collaboration with the Québec Ministry of Transport, they confirmed the feasibility and proposed a bridge in the estuary. They estimated the construction cost at 55 million dollars (1976 value), i.e. about 300 million dollars in 2025, and determined that a bridge would be more advantageous than maintaining a ferry crossing.
1979 – Study requested by the Minister of Transport, followed by an internal study carried out without the Minister’s knowledge

At the request of the Minister of Transport, Lucien Lessard, who was also the member for Côte-Nord, a study identified the optimal site for the construction of a bridge at the place known as La Boule, the narrowest point of the fjord’s estuary, already used by Hydro-Québec to carry a high-voltage line. However, without the knowledge of the Minister of Transport, an informal (or phantom) group of five people working internally at the Ministry, without clearly established professional qualifications, was formed. This group, led by a recently hired young urban planner, concluded that a bridge was not necessary, considering that Côte-Nord residents made little use of the road and preferred to fly. This informal study would contradict the study requested by the Minister and would allow Montréal members of the legislature, who wished to remove tolls on 3 metropolitan highways, to obtain the funds reserved for the Tadoussac bridge. As an alternative, the phantom group proposed adding ferries. Despite this orientation, they presented a bridge alignment in the immediate vicinity of the current ferry crossing. This option requires a much larger main span than that of La Boule (1,150 metres). The main span for the alignment near the ferries was wrongly estimated in this phantom study at 1,200 metres, whereas in reality subsequent studies show that the main span varies between 1,350 metres (2009) and 1,420 metres (1999). This difference of 200 to 270 metres in the main span largely explains the difference between a two-lane bridge, whose costs are much lower, as illustrated by similar bridges in Scandinavia, and a highway bridge.
Indeed, a bridge exceeding about 1,300 metres of main span requires a wider deck to stabilize it, particularly in strong winds. A bridge at the narrowest point of La Boule (1,150 m span) allows a much less massive structure with 2 traffic lanes and a multi-use path, as seen in Scandinavia (Hålogaland Bridge, 1,145 m, and Hardanger Bridge, 1,310 m, set in the mountains, sheltered from strong winds).
See the blog section of ponttadoussac.ca under the title “300 or 900 million for a bridge”.
1997 – Relaunch of the project
The Minister of Transport of the day, Jacques Léonard, announced the launch of an opportunity study for the construction of the bridge.
At the same time, the Société des Traversiers du Québec (STQ) announced a major refit and enlargement of its two Tadoussac ferries, increasing their capacity from 60 to 75 vehicle spaces.
1999 – Opportunity study

The study, conducted by the firm Buckland & Taylor / COWI, a recognized expert in the design of long suspension bridges, proposed a bridge near the current ferries. At the request of the Ministry of Transport, the La Boule site was excluded.
- Estimated cost of the bridge: $253M (1999) or $450M (2025), and
- Total project cost, including access roads: $370M (1999) or $653M (2025).
An accounting error inflated the cost of the La Boule option by $60 million (1999) or $106 million (2025), mistakenly making it uncompetitive.
2000 – Regional mobilization

Creation of the Société du Pont sur le Saguenay à Tadoussac, on the initiative of elected officials and stakeholders from all sectors of the Côte-Nord. Start of the review of the earlier studies.
2001 – Start of an impact study
The MTQ’s Côte-Nord regional office filed a project notice to launch an impact study on the construction of the Tadoussac bridge. Following the publication of the 1999 opportunity study, the two engineers in charge of the Ministry of Transport’s Côte-Nord regional office submitted a project notice to the Ministry in Québec City for the completion of the impact study on the construction of the bridge. Both individuals were transferred out of the region during the same period.
2009 – Environmental impact study
The project was entrusted to the SNC-Lavalin / Génivar consortium, with the collaboration of the engineer Michel Virlogeux. The proposed bridge is considerably larger than the former optimal option at La Boule, without any justification based on regional needs.
- Estimated cost: $712M (2003) or $1,120M (2025) for the bridge alone, and $809M (2003) or $1.3B (2025) for the two-lane bridge and its access roads. Alignment near the ferry crossing.
- For the La Boule alignment, the highway-bridge model described above near the ferries was taken and transposed as is to the mountain tops of the La Boule site, without even making the effort to optimize it for this narrower location. (Appendix 2005)
The chair of the BAPE hearings in Tadoussac in 2016 would describe the 2009 impact study as incomplete and therefore inadmissible for any future BAPE hearings.
2009 – Decision to acquire new ferries

In September 2009, 2 weeks after the publication of the impact study on the bridge, Minister Norman McMillan announced the construction of two new 110-vehicle ferries, without any public consultation or economic study. The STQ justified this decision by citing better service, although analysis shows:
- A longer boarding time
- A reduced frequency (20–25 minutes instead of 13 minutes with three smaller vessels (75 vehicles))
- A sharply rising operating cost
2015 – 2018
After meeting, in Norway and in Vancouver, the engineers responsible for the construction of the Hålogaland Bridge (Norway), the Société du Pont à Tadoussac presented a bridge project at the optimal site recognized since 1979, at the place known as La Boule: two traffic lanes and a multi-use path, at a cost far below that of 2009 — knowing that the Hålogaland Bridge was built at the tendered cost of $250M (2013), or $334M (2025), excluding approach roads and tunnels. The project was prepared in collaboration with the architect Pierre Brisset who, already in 1986, had presented a project to the Minister of Transport for a bridge at the La Boule site.
2018–2019 – Commissioning of the new ferries
The new ferries, including the required onshore works, were announced at a cost of:
- $170 million in 2009 ($242M (2025)); they were finally delivered in 2018-2019 at a cost of $434 million (2019), or $524M (2025): costs include the onshore works
- $177M per vessel
- $80M for the landing stages and onshore works
Since then, the operating costs of the Tadoussac crossing have exceeded $55M per year, and the service-interruption problems have not merely persisted; they have increased.
2017-2020 – Announcements and delays
2017: Premier Philippe Couillard announced a Project Office on August 24, 2017.
2018: Announcement of the start of the Office’s work by Pierre Arcand, Deputy Premier, and Véronique Tremblay, Minister for Transport. In the fall, a new government took office.
2020: The project office announced by the previous government became a group responsible for an “Enhancement of the 1999 opportunity study”.
Launch of the call for tenders for the “Enhancement of the 1999 study”, completed 20 years earlier, as well as for a socio-economic study.
2021-2025 – Enhancement study
The Project Office proposed by the previous government turned into a group supervising the Enhancement Study of the Opportunity Study carried out in 1999. This approach seemed promising, since the basis retained was the bridge project presented by the specialized firm COWI, which had estimated the cost of the bridge in 1999 at C$253M, i.e. about C$450M in 2025. Following the last-minute withdrawal of a partner able to liaise with the Ministry of Transport, the firm COWI was unable to take part in the call for tenders, and a French company that was working on the Québec City tramway project and on railway development projects on the Côte-Nord was selected to accompany 2 companies that had taken part in preparing the 2009 impact study. An additional Québec engineering company joined the consortium. The project presented had no other effect than to “enhance” the project cost upwards, since essentially the massive 2009 highway-bridge project was retained, replacing the 4 traffic lanes with 2 lanes plus 2 shoulders of 2.5 metres plus 2 bicycle paths of 3 metres each. The long span of nearly 1,400 metres requires the erection of a massive highway bridge of the calibre of the one presented in 2009.
That said, the bridge presented, although its exact dimensions are not yet known, has seen its cost rise from $712M (2004), i.e. $1,120M (2025), to $4.2 billion (2025), without it being possible to determine the details. The Société du Pont’s proposal at La Boule was not considered, for reasons yet to come. The firms selected did not have the expertise required to design and estimate the costs of such a bridge at La Boule. None had ever designed a two-lane bridge with a main span of more than one kilometre. As two of the companies had taken part in the design of the 2009 bridge project, they took up the project again, improving it, it seems, at least by substantially increasing the price, well beyond the mere effects of inflation.
For the time being, the study is being kept secret at the Ministry of Transport, although the Minister has assured that it will be made public so that the proposal can be understood and the extraordinary costs proposed can be explained.
In the 2025 study, it appears that the lowest-bidder rule prevailed over the choice of expertise proven by projects completed elsewhere. This could explain the large price differences between the latest proposed project and the earlier ones. Otherwise, how else can one explain that the same bridge project, at the same location, goes from $653M to $4,200M in constant 2025 dollars?
Many questions remain unanswered, because the costs mentioned do not seem to correspond at all to the costs of similar projects internationally. The Minister of Transport and the Premier have acknowledged that these costs could be substantially reduced. As the Société du Pont sur le Saguenay à Tadoussac has been working on a volunteer basis for 25 years towards the realization of this project, it asks that the study be made available quickly so that citizens can review it and comment on it as needed. The Minister has committed to doing so, but has not said when. The last study, from 2009, had been completed since 2005 and was only made public 4 years later, at the same time as the announcement of the construction of two new ferries at Tadoussac — ferries that contribute to the deterioration of fluid and safe access to the Côte-Nord region.
2025 – Reassessment and the Minister’s statement
The Minister of Transport announced an estimated cost of 4.2 billion dollars for the bridge, without making public the study behind this figure.
| Year | Study | Cost of the bridge | Total project cost |
|---|---|---|---|
| 1999 | Opportunity study | $253M or $450M (2025) | $370M or $653M (2025) |
| 2009 | Impact study | $712M or $1,120M (2025) | $809M (2003) or $1,300M (2025) |
| 2025 | Enhancement of the study | $4,200M (2025) | study not disclosed, so the cost of the bridge remains to be confirmed |
The people of the Société du Pont wish to review the “Enhancement” study to understand how a cost of this magnitude could have been arrived at.
Conclusion
The Minister of Transport and the Premier acknowledge that the cost of the project is high but that it can be reduced. Despite this, both have acknowledged that it is a good project. The Minister has committed to sending one or more independent experts abroad as early as 2026 to study and propose avenues for reducing costs while limiting delays and execution risks. It is known that the construction abroad of bridges similar to the one required at Tadoussac has cost much less than the price put forward by the Minister. The methods of intervention, new technologies and ways of doing things must be studied. Nothing indicates, however, that the results of this international research will serve the Tadoussac bridge project in the short term.
In the current context, the priority seems to be the third link in Québec City and the East tramway in Montréal. The argument is put forward that the bridge project depends on the participation of the federal government, which is surprising given that the completion of several major infrastructure projects elsewhere — including the construction of the third link in Québec City and the new Île d’Orléans bridge, among others — does not a priori depend on federal participation. It is not specified whether this is a pretext, like the argument that there is no more money for the project, when in the same breath investments of tens of billions are announced for the third link in Québec City and for a tramway project in the east of Montréal. Moreover, ending the ferry service will generate savings in public funds throughout the life of the bridge. Currently, with annual costs approaching $60M, it can be estimated that, over the bridge’s 200-year lifespan, like that planned in Europe for similar bridges, the savings in constant dollars for Québec taxpayers over the next 200 years will be 12 billion dollars from the moment the ferry service stops.
Premier François Legault acknowledges that the estimated cost is high, but describes the project as a “good project” that remains listed in the Québec Infrastructure Plan (PQI), while announcing a freeze of at least 5 years on the bridge construction project. No funding and no progress would be possible until then.
The Société du Pont sur le Saguenay and the Coalition Union 138 are continuing their efforts to unblock the construction of the bridge. It is a laborious process spanning nearly a hundred years. The main obstacle is political and stems from a lack of understanding of the territory and its environment, as well as from the impossibility of allowing international competition without it being subject to the constraints and costs established by Québec engineering firms. In government circles, the Côte-Nord is perceived as a place of extraction sites and resource shipping rather than as a place where people live — including the Indigenous peoples who have inhabited it for thousands of years. North Shore residents also wish to benefit from the spin-offs of these resources. To ensure a prosperous future for the generations to come, they must have, at a minimum, a road completed at both its ends, at Tadoussac and on the Lower North Shore towards the neighbouring province. It is an essential condition for the reasoned and sustainable development of those who, still, at arm’s length, keep this rich and vast territory alive — from which Québec would have everything to gain.
“Those who do not know history are condemned to repeat it.”
Winston Churchill