By Pierre Breton
People have been calling for a bridge at the mouth of the Saguenay since 1909. Since at least 1927, it has been promised during election campaigns: Donat Bouchard, a campaign worker for candidate Edgar Rochette in the 1927 election in Charlevoix-Saguenay, testified to this. This year again, every party says it is in favour; on March 26, 2025, the National Assembly even unanimously adopted a motion recognizing that building a bridge is necessary1. Promises are no longer enough.
It is time to free the people who shape the choices at the Ministry of Transport (MTMD) from the regulatory straitjacket that has built up over decades. New governments must learn to take better account of regional realities when choosing which benefits are counted in the ministries’ cost-benefit analyses. Benefits are not the same in the city as in the regions. Those who shape these choices should become familiar with the imperatives of developing the territory, a far more realistic approach than measuring the benefits of a road infrastructure solely by the urban criteria of the number of vehicles and the time lost per passenger. As our relations with our American neighbour deteriorate, the dynamism of every region must be put to use. The current one-way relationship, which aims to extract as much in royalties as quickly as possible without returning a fair share to develop the region, cannot go on forever. The regions should not exist to support the metropolis and the large cities: a fair sharing must be rethought.
In this context, here are three specific questions to ask your candidates.
The facts
On August 24, 2017, Premier Philippe Couillard announced a project office for the bridge2. The next government turned it into an “enhancement” of the 1999 opportunity study. On April 29, 2025, the Minister of Transport presented a cost of $4.2 billion without publishing the study, despite the National Assembly’s unanimous motion3. A few weeks earlier, on April 1, 2025, the ministry had announced that no money would be allocated to the project before 20304. The bridge remains listed as “under study” in the Québec Infrastructure Plan5.
Several elements of the earlier studies skewed the results of the analyses and wrongly discredited the case for building a bridge quickly: the choice of discount rate; the calculation of the costs actually avoided by ending the ferry service; an analysis period that is too short, which, according to what has been reported about the 2025 study, would count only 23 years of benefits after the bridge opens; and economic spin-offs measured almost exclusively by the number of vehicles, an urban notion that cannot be applied as such to a territory as rich and vast as the North Shore and Labrador. We discussed this in two recent articles: “Bridge or ferries at Tadoussac: what the numbers say” and “The hidden number that decides the fate of the Tadoussac bridge”.
Question 1: Will you publish the 2025 study in full, and when?
Without the study, no one can check where the $4.2 billion figure comes from or how to reduce it. Premier Legault acknowledged it himself in January 2025: “Some of the figures are very high, but we think it is possible to do this at a lower cost6.” Premier Christine Fréchette’s team now promises an international call for interest to see what prices and optimized designs can be obtained7: that is an admission that the figure can come down. Serious parties should demand the study before taking a position on what looks very much like an effort to please voters before the election, only to put the project back to sleep afterwards.
Question 2: Will you let international competition propose the best bridge, at the best price, in the best location?
An international call for interest is a good idea, but not if it imposes in advance the massive bridge of 2009 and 2025: for example, 110 metres of clearance under the deck instead of the 75 to 80 metres of international standards, and two 2.5-metre shoulders. As early as 1999, the firm Buckland & Taylor (now COWI) considered the 88-metre height then planned excessive and recommended lowering the deck to reduce costs8. The firms that designed Hålogaland, Hardanger or Höga Kusten know how to do it. Our companies could carry out most of the work: roads, piers, anchorages. Foreign expertise is needed only for the steel structure, which, according to our estimates based on the Norwegian bridges, accounts for less than a third of the project’s expected cost. It is nonetheless essential to obtain the best value in terms of quality, price and schedule.
Question 3: Will you make completing Route 138, at Tadoussac and on the Lower North Shore, a project of national interest in which the federal government can take part?
Route 138 is the interprovincial link to Newfoundland and Labrador and its nearly 550,000 inhabitants9. It is blocked at both ends: at Tadoussac and on the Lower North Shore. With the August 2026 agreement on the Churchill River (nearly $70 billion)10 and the major mining, port and hydroelectric projects, traffic can only increase. Since 2025, Ottawa has had a law to speed up projects of national interest11; since 2024, Québec has had Mobilité Infra Québec and new delivery methods1213. The Tadoussac bridge and Route 138 are not on these lists. Who will commit to putting them there?
Why it is so difficult
The heart of the problem is the bureaucracy that prepares and steers decisions within a rigid framework designed by and for cities. Politicians come and go; civil servants stay. They prepare cost-benefit analyses that, depending on their interests and sometimes on politicians’ requests, make projects live or die. This is nothing new: in 1979, Transport Minister Lucien Lessard, who wanted to build the bridge, saw the analysis by the engineers of LGL contradicted by a study prepared without his knowledge by a small internal group at the ministry (the 1979B study), while Montreal MNAs wanted to use the bridge funds to abolish the tolls on three metropolitan highways. Lucien Lessard told the story himself in an open letter published in North Shore newspapers, reproduced in appendix B10 of the 1979B study14.
Jobs tied to the ferry will end, as everywhere a bridge has replaced ferry boats. But a smooth and predictable road will create far more, in tourism, transportation and resource processing.
Politicians need courage to demand the study and accept that its figures be questioned. North Shore and Charlevoix residents, ask your candidates these three questions. Charity begins at home: a completed road is an essential condition for stopping the region’s decline.
The time has come to rethink how Québec’s regions are developed, all the regions. To develop them, not just to grow extraction and shipments.
Sources
- CIMT (Jérôme Gagnon), March 26, 2025, motion adopted unanimously, in French: cimtchau.ca
- Radio-Canada, August 24, 2017, Philippe Couillard promises a project office, in French: ici.radio-canada.ca
- Le Soleil, April 29, 2025, “$4.2 billion for a bridge over the Saguenay”, in French: lesoleil.com
- Le Manic, April 1, 2025, “Saguenay bridge: project on hold”, in French: lemanic.ca
- Journal Haute-Côte-Nord, March 18, 2026, the bridge still “under study” in the Québec Infrastructure Plan, in French: journalhcn.com
- Le Manic, January 31, 2025, the Premier on the Saguenay bridge, in French (quotation translated by us): lemanic.ca
- Ma Côte-Nord, September 3, 2026, international call for interest, in French: macotenord.com
- Buckland & Taylor, Saguenay River Crossing Feasibility Study (1999 opportunity study), section 8 “Recommendations”, p. 42: photo of page 42; see also appendix E, p. E13: image
- Government of Newfoundland and Labrador, population as of April 1, 2026 (547,910): gov.nl.ca
- Office of the Prime Minister of Canada, August 17, 2026, Churchill Falls and Gull Island projects: pm.gc.ca
- Government of Canada, Building Canada Act (projects of national interest), 2025: canada.ca
- National Assembly, Bill 61 (Mobilité Infra Québec), in French: assnat.qc.ca
- National Assembly, Bill 62 (infrastructure project delivery methods), in French: assnat.qc.ca
- 1979B study, excerpts from appendix B (open letter by Lucien Lessard: appendix B10), in French: PDF
Quotations from French-language documents are our translation.


Leave a Reply