The hidden number that decides the fate of the Tadoussac bridge

Published on

by

in

, , , ,

By Pierre Breton

They say numbers speak for themselves. They also say you can make them say anything. The studies on the Tadoussac bridge are a good example. Change a single number in the cost-benefit analysis (CBA) and a project looks either profitable or not: the discount rate.

A rate that decides whether a project lives or dies

The discount rate reduces, year after year, the value of a project’s future benefits and costs. The higher it is, the less the savings made in 20, 50 or 100 years count, while construction costs, paid at the start, keep their full weight. For a bridge that will last more than a hundred years, this choice is decisive. And economists do not agree on it: the analyst, or the client, makes the choice.

Who pays for the study, and who signs it?

Economist Philippe Barla, of Université Laval, writes it in his textbook on cost-benefit analysis: “Assessing the quality of a CBA begins by determining who funded it and the credibility of its authors.” He adds that the client can “demand” an answer that justifies a decision already made. And the example he gives is… our bridge: the consortium that produced the 2009 study “was made up of engineering firms that could have been hired to build the bridge.”1

So let us ask the question. Génivar, now WSP, took part in the 1999, 2009 and 2025 studies. SNC-Lavalin, now AtkinsRéalis, signed the 2009 study. The largest shareholder of both firms is the Caisse de dépôt et placement du Québec, a Crown corporation: it holds 13.9% of WSP and 16.7% of AtkinsRéalis, and no other shareholder exceeds 10%.23 The same government is responsible for the Société des traversiers du Québec, whose service the bridge would replace. At the very least, this is an appearance of a conflict of interest.

It may be no coincidence that the 2009 study presented a much more massive bridge, two to three times more expensive than the 1999 one: $712M for the bridge alone, versus $253M, and up to 140 metres of clearance above the water, versus 88 metres (see the comparison, appendix F, p. F29).4 The 1999 bridge had been designed by Buckland & Taylor, a subsidiary of the Danish firm COWI, one of the world’s leading references for large suspension bridges: it designed the 1915 Çanakkale Bridge in Turkey, the longest in the world, the Hålogaland Bridge in Norway and the Strait of Messina bridge project in Italy.5 The ministry knows it well: COWI is part of the consortium it retained for expert work on the Pierre-Laporte Bridge.6

In 2020, COWI wrote to the ministry to offer its expertise for the study that led to the 2025 figure (file 3403-19-AA01).7 Its letter is telling: only “a handful of bridge consulting firms” can credibly assess the costs and risks of such a bridge; yet the call for tenders required “only one engineer with a minimum of 10 years of experience on at least 2 projects in similar conditions,” without defining what a long-span bridge is. COWI tried to team up with Québec firms, without success, and warned the ministry that this lack of experience “could easily lead to erroneous conclusions and ill-informed decisions” about the bridge’s form, costs and risks. It proposed hiring a specialized firm as owner’s engineer. COWI also deplored that the call for tenders required all team members to be members of the Ordre des ingénieurs du Québec, which excluded its suspension bridge specialists in Denmark and North America. The consortium that was retained (SYSTRA, CIMA+, WSP) has, for its part, one reference in kilometre-long suspension bridges: the Chacao Bridge in Chile, designed by SYSTRA with Aas-Jakobsen, whose contract was signed in 2014 and which is now scheduled to open in October 2028.8

The ministry’s tendency to inflate the figures of projects it does not want is known as far as Québec City: in 2016, Mayor Régis Labeaume publicly warned it “not to inflate the figures” of the study on the third link. “We know the trick,” he said (appendix F, pp. F57-F58).9

Now back to the discount rate: let us see what it has done to the bridge over the past 25 years.

1999: 8%, a very high rate for infrastructure built to last more than a century

The 1999 opportunity study announces a 5% rate, but the reference scenario is calculated at 8%. Result: a benefit shortfall of $168M and a benefit-cost ratio of 0.60.10 The project was buried without its parameters ever being discussed, several of which are highly questionable.

2006-2009: from -$233M to -$89M

In April 2006, the Ministry of Transport presented a preliminary version of the impact study to the media: a deficit of $233M over 40 years, calculated at 6% (see the article of April 21, 2006, appendix F, p. F48).4 Neither the Société du Pont nor other stakeholders had been consulted. Our volunteers found several errors and omissions: accidents on the Charlevoix side, on the approach to the ferry, had been left out; the life of a North Shore resident was valued at $3.6M, while another ministry study at the same time valued the life of a Route 175 user heading to the Saguenay at $5M.

In January 2007, the Société du Pont asked in writing for a 4% rate, “given the service life of the proposed structure, which will be more than 100 years.” In October 2007 the ministry replied that a 5% rate should be considered “given that the bridge is a very long-term investment, that is, for future generations” (exchange of letters, appendix F, pp. F15 to F28).4 With this rate and the accepted corrections, the balance improved by $144M (more than $200M in today’s dollars): the deficit went from $233M in the preliminary version to $89M in the final version published in 2009.11 These corrections never got the media coverage of the 2006 figure.

“A lie can travel halfway around the world while the truth is putting on its shoes.” (attributed to Mark Twain)

A few weeks later, on September 8, 2009, the Minister Delegate for Transport, Norman MacMillan, announced in Baie-Comeau the construction of two large ferries to replace the three existing vessels, which were still serviceable for decades to come.26

The most revealing part is in the 2009 study itself. In its sensitivity analysis, moving from 5% to 4% is enough to make the balance positive: +$21M, with a benefit-cost ratio of 1.03. Its authors in fact recommended the bridge “from a long-term and sustainable development perspective (with a discount rate of around 4%).” And valuing a life at $5M reduced the deficit by nearly $24M.12

Double standards

In 2011, for the replacement of the Champlain Bridge in Montréal, the BCDE consortium’s pre-feasibility study used a 3.3% rate, “the one currently used by the MTQ in the analysis of its projects.”13 Two years earlier, 5% was applied to Tadoussac. Today, the Ministry of Transport’s own cost-benefit analysis guide (2023) sets the rate at 2.7% in real terms.14 In Norway, transport infrastructure is assessed at 4% for the first 40 years, then 3% and 2% beyond.15

We redid the calculation with the annual flows published in the 2009 study itself (table F.14), changing nothing but the rate. At 3.3%, Montréal’s rate in 2011, the bridge produces a net benefit of $125M (benefit-cost ratio of 1.16). At 2.7%, the ministry’s current rate, the net benefit reaches $236M (ratio of 1.29).16 Even with its own 2009 figures, the bridge is profitable as soon as it is judged by the metropolis’s rules. Why should a bridge in the regions be judged with a rate almost twice as high as a bridge in Montréal?

Do the math yourself. Our interactive calculator takes the official figures of the 2009 study (table F.14) and lets you choose the discount rate: at 5%, the bridge loses $89M; at 4%, it gains $21M; at 3.3%, the rate used for the Champlain Bridge, $125M; at 2.7%, the ministry’s current rate, $236M.

And the 2025 study? It has never been published. Officially, we know neither its discount rate, nor its analysis period, nor its benefit-cost ratio. In preliminary discussions, a 6% rate and a benefit-cost ratio of about 0.70 were mentioned; these figures remain to be confirmed when the study is published. If they are accurate, they alone explain the negative verdict: a rate suited to a 30-year road project wipes out the long-term benefits of a bridge that will last more than 100.

Other parameters work in the same direction: an analysis period of 30 or 40 years for a structure that will last more than 100; construction years during which the cost of the bridge is added to that of the ferry (the ministry plans seven years of construction);17 ferry costs assumed to follow inflation when they have exceeded it by 5% a year from 1999 to 2024 (from $18M to $62M in 2024 dollars according to STQ annual reports, +238% in real terms);18 benefits measured almost solely in waiting minutes per vehicle, with no regard for the economic spin-offs of a completed road to Newfoundland and Labrador, or for the region’s major projects, including the nearly $70B Churchill Falls and Gull Island projects announced on August 17, 2026 (final agreements still to be signed).19

A Québec model that penalizes the regions

This is no accident. Québec’s regional development model has rested since 1970 on the Higgins, Martin, Raynauld study (HMR70), commissioned by the federal government, which reserved “development” for Montréal and mere “growth” for the other regions (appendix F, p. F74 and following).20 “Growth” must be understood in the sense of this model: extracting and shipping resources, with no need to develop the community. Stadiums, opera, metro and REM are reserved for the metropolis. Economist Fernand Martin, co-author of that study and a convinced centralizer, taught for more than fifty years in the economics department of the Université de Montréal, where many of the economists who prepare the government’s cost-benefit analyses were trained. His work is also a reference at the Ministry of Transport: three of his publications, including “Faiblesses, embûches et abus dans les analyses avantages-coûts” (1993), are listed in the bibliography of the ministry’s cost-benefit analysis guide (2006 edition, published in 2008).25 In our view, given his public positions on remote regions, there is reason to question his objectivity and the relevance of Québec’s regional development model, to which he contributed through the HMR70 study. In 2001, he still told La Presse: “Whatever angle you take, […] it is clear that Québec’s regions do not produce enough wealth to support the people who live there.”21 In 2003, economists Mario Polèse and Richard Shearmur observed the failure of this model (“R.I.P.-H.M.R.”).22 Yet it is still applied.

The facts say the opposite of Fernand Martin: according to an Aviseo study published in August 2026, the North Shore pays the government between $930M and $1B more each year in tax revenue than it receives in public spending.23

What we are asking for

That the 2025 study be published in full, with its cost-benefit analysis: discount rate, analysis period, actual cost and actual growth of ferry costs, value of human life, accidents taken into account. That the Tadoussac bridge be subject to the same rules as projects in the metropolis: with the ministry’s own rules, the result would be very different.

And that the international call for interest be addressed to companies recognized for designing and building kilometre-long suspension bridges, giving them full latitude to propose the site and project they consider optimal. The Société du Pont has long proposed the narrowest site on the river, at the place known as “La Boule,” recommended by the firm LGL in 1979: 200 metres shorter changes everything on costs. It also proposes a clearance of 75 to 80 metres, close to that of the 1999 project (88 metres), a height that Buckland & Taylor/COWI in fact recommended lowering toward international standards (appendix E, p. E13),24 rather than the 140 metres of 2009. An open call for interest would make it possible to optimize the project, its price and its timeline, while reducing risk. We would finally have an independent point of view, sheltered from pressure by interest groups.

Sources

  1. Barla, P. (2024), Introduction à l’analyse coût-avantage, Université Laval, section 2.2, first paragraph (in French): pressbooks.etsmtl.ca
  2. WSP Global, 2026 management information circular (Caisse de dépôt: 13.87%, p. 8 of the document): wsp.com (PDF)
  3. AtkinsRéalis, 2026 proxy circular (La Caisse: 16.71%, p. 11 of the document): atkinsrealis.com (PDF)
  4. 2009 impact study, excerpts from appendix F: 1999-2004 comparison (p. F29), article of April 21, 2006 (p. F48), 2007 exchange of letters (pp. F15-F28), table F.14 (pp. F8-F9), in French: PDF
  5. COWI: 1915 Çanakkale Bridge; Strait of Messina bridge final design; Hålogaland Bridge: cowi.com ; strettodimessina.it ; structurae.net
  6. Radio-Canada, Pierre-Laporte Bridge expert contract (CIMA+, Tetra Tech, COWI), in French: ici.radio-canada.ca
  7. COWI North America, letter to the Ministry of Transport, file 3403-19-AA01, summer 2020 (acknowledged by the ministry on August 6, 2020), in French: PDF
  8. Chacao Bridge (Chile): SYSTRA project sheet; Chilean Ministry of Public Works, July 30, 2026 (opening scheduled for October 2028): systra.com ; mop.gob.cl
  9. Radio-Canada, 2016, Régis Labeaume and the third-link study (appendix F, pp. F57-F63), in French: PDF
  10. 1999 opportunity study (Naturam-Génivar), cost-benefit analysis, scenario 3: Studies section: our site; excerpts from appendix E of the studies table, p. E12 (in French): PDF
  11. Le Soleil, August 19, 2009 (2006 preliminary study: -$232M; final study: -$89M over 40 years), in French: lesoleil.com
  12. SNC-Lavalin–Genivar consortium (2009), impact study of the Saguenay River bridge, table 5.3 (sensitivity analysis 2006-2046: 5%: -$89.5M; 4%: +$21.2M; life valued at $5M: -$65.7M): our site
  13. BCDE consortium (2011), pre-feasibility study for the replacement of the Champlain Bridge, sector report no. 8, p. 31 (see also appendix F, p. F54), in French: bv.transports.gouv.qc.ca (PDF) ; PDF
  14. Ministère des Transports et de la Mobilité durable, cost-benefit analysis guide for public road transport projects, 2023, in French: transports.gouv.qc.ca (PDF)
  15. Norway, Ministry of Finance, circular R-109/2021, section 6.2 “Kalkulasjonsrente” (rates 4%, 3%, 2%): regjeringen.no (PDF, in Norwegian). Our translation: “For other government measures, the risk-adjusted discount rate shown in the table is to be used: 4.0% for years 0 to 40, 3.0% for years 40 to 75 and 2.0% after 75 years. Growing uncertainty about the alternative return is taken into account by lowering the discount rate after 40 years.”
  16. Recalculation by the Société du Pont from table F.14 (net flows 2006-2046): 5%: -$89.5M (identical to the study); 4%: +$21.2M (identical); 3.3%: +$124.8M (BCR 1.16); 2.7%: +$235.8M (BCR 1.29). Online calculator: our site
  17. Journal Haute-Côte-Nord, March 1, 2026 (schedule: seven years of construction), in French: journalhcn.com
  18. STQ, annual management reports 1999 to 2024, costs of the Tadoussac–Baie-Sainte-Catherine ferry, converted to 2024 dollars (compilation by the Société du Pont; 2024-2025 report, p. 43): traversiers.com (PDF)
  19. Office of the Prime Minister of Canada, August 17, 2026, Churchill Falls and Gull Island projects (nearly $70B): pm.gc.ca
  20. Higgins, B., Martin, F., Raynauld, A. (1970), Les orientations du développement économique régional dans la province de Québec, Department of Regional Economic Expansion (excerpts: appendix F, p. F74 and following): PDF
  21. Hélène Baril, “Les lois du marché ont raison des régions éloignées”, La Presse, Business section, p. E2, Saturday, December 8, 2001, in French: copy of the article (image)
  22. Polèse, M. and Shearmur, R. (2003), “R.I.P.-H.M.R. : à propos du concept de pôle de développement…”, Canadian Journal of Regional Science, 26(1), in French: idjs.ca (PDF)
  23. Le Manic, August 31, 2026, “La Côte-Nord verse un milliard par année en surplus au provincial” (Aviseo study), in French: lemanic.ca
  24. 1999 opportunity study, appendix E, p. E13 (Buckland & Taylor/COWI recommendation to lower the deck): image
  25. Ministère des Transports du Québec, Guide de l’analyse avantages-coûts des projets publics en transport, part 1: methodological summary (2006, legal deposit 2008), bibliography, p. 56 of the document (p. 68 of the PDF) (three works by Fernand Martin), in French: bv.transports.gouv.qc.ca (PDF)
  26. Société des traversiers du Québec, 2009-2010 annual management report: in September 2009, in Baie-Comeau, Minister Delegate for Transport Norman MacMillan announced $400M for the construction of three vessels, two of them for the Tadoussac–Baie-Sainte-Catherine crossing, in French: traversiers.com (PDF); press release of September 8, 2009, “Le gouvernement du Québec investit 400 M$ pour la construction de trois navires” (BAPE, Tadoussac dolphin project, 2016, document DA10), in French: archives.bape.gouv.qc.ca (PDF)

Quotations from French-language documents are our translation.

Comments

One response to “The hidden number that decides the fate of the Tadoussac bridge”

  1. […] omissions, biases and errors add up in these analyses; I come back to this in another text, “The hidden number that decides the fate of the Tadoussac bridge“. There is an English expression for this: garbage in, garbage […]

Leave a Reply

Your email address will not be published. Required fields are marked *