Bridge or ferries at Tadoussac: what the numbers say

Published on

by

in

, , , ,

By Pierre Breton

A few days before the October 5 election, the $4.2 billion price tag put forward in April 2025 for the bridge over the Saguenay is circulating as an established truth. The study behind it has never been published. The figures for the Tadoussac ferry, on the other hand, are public. Let us put them side by side.

A ferry that costs almost twelve times more than in 1973

In 1973, the Tadoussac ferry cost about $790,000 a year, according to documents of the Société des traversiers du Québec (STQ). Adjusted for inflation, that is about $5.4 million today. In 2023-2024, the STQ reported a cost of $62.5 million for this crossing alone ($54.9 million in 2024-2025, a year without the mandatory dry-dock work). In constant dollars, the ferry therefore costs almost twelve times more than fifty years ago: real growth of about 5% a year, over and above inflation.

Forecasts far removed from reality

In its cost-benefit analysis, the 1999 feasibility study counted the end of the ferry as a fixed saving of $6.8 million a year, the same every year for 30 years, or $11.8 million in today’s dollars. The reality in 2023-2024: $62.5 million, more than five times as much, and that is without counting the Tadoussac crossing’s share of the STQ’s unallocated costs. The 1999 and 2009 studies wrongly assumed that the cost of the ferry would simply follow inflation. Yet these costs avoided by stopping the ferries are the main counterweight to the cost of a bridge in a cost-benefit analysis. No wonder the result comes out negative, all the more so since several other omissions, biases and errors add up in these analyses; I come back to this in another text, “The hidden number that decides the fate of the Tadoussac bridge“. There is an English expression for this: garbage in, garbage out.

A service less reliable than it seems

In 2011-2012, the ferry cancelled 381 crossings (STQ figures filed with the BAPE, Quebec’s environmental public hearings office, in 2016). According to the STQ’s annual reports, it cancelled 1,838 in 2022-2023, 3,213 in 2023-2024 and 1,935 in 2024-2025, five to eight times as many. I leave aside the two COVID years, when cancellations exceeded 4,400 a year. The STQ reports a “completion rate” that looks reassuring. But that rate includes evening and night crossings, when demand is low. It is during the day, in summer and on long weekends that the service has to deliver. The second ship makes about 33 crossings a day: since 2022, the cancellations amount on average to 71 days a year with only one ferry in service, every 40 minutes. One day in five. With the platoons of cars leaving the ferry, the heavy trucks and the race not to miss the boat, this is what coroner Arnaud Samson already called in 2001 the “ferry syndrome”, with the accidents, deaths and injuries that go with it. The Ministry of Transport’s figures filed with the BAPE confirm it: on the 36 km between Saint-Siméon and the Baie-Sainte-Catherine wharf, accidents rose from 136 (2004-2009) to 191 (2010-2015), an increase of 40%, including two fatal accidents.

Two new ferries at 2.6 times the contract price

In 2009, two weeks after the publication of the bridge impact study, the government announced two new ferries for Tadoussac, with no consultation and no known prior analysis. At the 2016 BAPE hearings, the STQ could not find any document predating that decision: only the press release and the speech from the September 8, 2009 press conference with the Minister for Transport, Norman MacMillan (hearing transcripts DT1, pp. 21-31, and DT2, pp. 10-11). The firm contract was $125 million for both ships; their cost finally reached about $324 million (Le Soleil and Le Manic, 2018). In summer, three ships of 72 vehicles each loaded every 13 minutes, close to 330 vehicles an hour. The two new ships of 110 vehicles each, every 19 or 20 minutes, offer about the same: the BAPE wrote in black and white in 2017 that at the summer peak “the capacity […] would remain the same”. According to what the STQ’s CEO at the time, Georges Farrah, told us at a meeting in the office of MNA Marjolain Dufour, the decision was made in Premier Jean Charest’s office in March 2009, notably to give work to the Davie shipyard; Marc Gilbert, then president of the Société du Pont, also reported it in his brief to the BAPE in 2016. At the hearings, the STQ spoke of a “political decision” that it merely carried out, and the Ministry of Transport’s representative said: “we go with the flow”. Asked about the effect of exit platoons some forty vehicles longer on Route 138, the ministry, according to the BAPE report, “is not in a position to comment”: no study had been done, and it intended to “monitor the situation”. The old ferries, for their part, still sail at the Sorel crossing.

The price of the bridge: from one to six

Same bridge, same location, three estimates:

  • 1999, feasibility study (Naturam-Génivar consortium, design by Buckland & Taylor/COWI): $253 million for the bridge, $370 million with the access roads, about $450 million and $655 million in 2025 dollars;
  • 2009, impact study (SNC-Lavalin/Génivar): $712 million for the bridge alone, between $875 and $902 million for the complete project, about $1.1 billion in 2025 dollars for the bridge;
  • 2025, “enhanced” feasibility study (SYSTRA, CIMA+, WSP): $4.2 billion, presented on April 29, 2025. The study has not been published, despite a unanimous motion of the National Assembly on March 26, 2025, which recognizes that building a bridge is necessary and asks the government to “disclose the feasibility study in its possession”.

In constant dollars, the price has been multiplied by more than six since 1999. Yet elsewhere, bridges of this type are built for a fraction of that price. The Hardanger Bridge in Norway (2013), with a free span of 1,310 metres, replaced a ferry for 2.5 billion Norwegian kroner, about CAD 370 million at today’s exchange rate. The Hålogaland Bridge (2018), with a 1,145-metre span, cost 2.2 billion kroner, about CAD 330 million. And Norway is one of the countries with the highest cost of living in the world.

Nobody knows what the $4.2 billion figure includes. Financing costs? Maintenance over 30 years? Contingencies? When you buy a $30,000 car, you do not say it costs $60,000 because you will have to change the tires and the oil and pay interest for 10 or 15 years. And unlike the new Île d’Orléans bridge (a $2.76 billion project, of which almost $0.9 billion comes on top of the $1.88 billion construction contract, notably to deconstruct the old bridge), the Tadoussac bridge has no old bridge to demolish: it replaces a recurring annual expense that has grown by almost 5% a year above inflation for fifty years. The interactive table of studies on our website gives, in 2025 dollars, the price of every bridge project presented since the beginning: the 2025 price is completely off the chart. Comparing with similar bridges built elsewhere in the world shows the same inconsistency, for a price set by firms that, to my knowledge, have never completed a suspension bridge with a span of more than one kilometre.

What the bridge would bring

Stopping the ferry means saving about $60 million a year. If that cost keeps growing by 4.9% a year above inflation, as it has for fifty years, the savings reach almost $4 billion over 30 years. And a modern, well-maintained suspension bridge lasts 100 to 200 years: over 200 years, even without any growth, that is $12 billion in constant dollars saved by Quebec taxpayers.

The real figures for the ferry and the real costs of similar bridges elsewhere already justify building the bridge. What remains is to make the 2025 study public so that it can be discussed, and to ask international competitors for prices, without constraints that prevent them from proposing the best option. On September 3, Christine Fréchette’s team committed to launching an international call for interest within its first 100 days: a step in the right direction, provided the study is published and the specifications remain open. The new Premier, Paul St-Pierre Plamondon, committed during the campaign to building the bridge and breaking ground before 2030*. That will be difficult if users, local stakeholders and informed citizens are not consulted. It may seem presumptuous to hope to do better than Transport Minister Lucien Lessard, who in 1979 saw the analysis by the engineers of LGL discredited by a secret study by his own officials, carried out without his knowledge, in order to transfer the funds earmarked for the Tadoussac bridge to Montreal and abolish 25-cent tolls on three highways. I am nonetheless convinced that if the real figures are presented to the National Assembly, construction of the bridge will quickly get under way, for the benefit of all Quebecers. What is needed now is the goodwill of everyone involved to obtain the real figures and an objective treatment that fully informs decision-makers. The path is laid out; all that remains is to take it.

Sources

Comments

One response to “Bridge or ferries at Tadoussac: what the numbers say”

  1. […] as rich and vast as the North Shore and Labrador. We discussed this in two recent articles: “Bridge or ferries at Tadoussac: what the numbers say” and “The hidden number that decides the fate of the Tadoussac […]

Leave a Reply

Your email address will not be published. Required fields are marked *