A BRIDGE AT TADOUSSAC: $300 MILLION OR $900 MILLION?

Published on

by

in

, ,
Vues latérales comparées des ponts proposés à La Boule et près des traversiers
Elevation of the proposed bridge towers with dimensions

” What need is there for the bridge to be broader than the flood? The necessary is always the fairest of concessions.” William Shakespeare (ed. 1591)

When we speak of the cost of building a bridge over the Saguenay, at the optimal site determined by engineers since 1979, at “La Boule”, very different assessments circulate. Thus, depending on the interested parties — Société du Pont sur le Saguenay (SPS 2015) / COWI International Engineering vs. the SNC-Lavalin/Génivar consortium in the 2009 Impact Study (SNC 2009) — the price of a bridge triples.

Map from the 1999 study: alignments P1 (La Boule) and P4 (near the ferries)

Why such a gap? Quite simply because we are talking about two (2) completely different projects. One, SNC 2009, proposed under multiple constraints from the Québec Ministry of Transport (no tunnel, 4-lane highway, etc.); the other prepared by local people with the help of the firm COWI, whose expertise in the design of long suspension bridges has long been known internationally. This firm was retained by the Ministry of Transport to propose a bridge at Tadoussac as part of the 1999 Opportunity Study. Already familiar with the area, these experts are among the few able to design long two-lane suspension bridges. The examples of the Hålogaland Bridge in Norway, which they designed, and of the Höga Kusten Bridge in Sweden demonstrate their seriousness when they assert that a bridge at Tadoussac will cost less than $300M if Québec calls for international tenders from companies specializing in the construction of such structures.

The bridges proposed at the optimal site of La Boule

SNC 2009 project

A 4-lane highway bridge without a sidewalk, a very high deck (112 to 140 metres) with a 2.1% slope passing over the mountains (no tunnel), with a massive structure. Note that this bridge is almost identical to the bridge proposed in 2004 by the consortium at a site near the ferries and published in the impact study only in 2009. The consortium made no effort to optimize the structure for the La Boule location. The bridge presented is therefore 200 metres longer than necessary (1,350 metres instead of 1,150 metres), with 10 metres more carriageway width than necessary — a highway instead of a road — and 70 metres higher than necessary, which overall triples its cost. See the MTQ document on the constraints above.

SPS 2015 project

A 2-lane bridge, with a tunnel, therefore lower, and a sidewalk on a multi-use path, implying a less massive structure using a new concept and consequently much smaller quantities of steel and concrete. E.g.: Hålogaland Bridge, Norway. (See video at the end of the blog or here)

Since a picture is worth a thousand words, we have set out in images the main parameters of these 2 projects to make them easier to compare (see: Table A – Elevation and plan view, and Table B – The pylons)

Comparative side views of the bridges proposed at La Boule and near the ferries

For those who wish to take the analysis a little further, consult the following documents:

  1. The technical sheet of the Norwegian Hålogaland Bridge suggested by the experts for the Tadoussac site
  2. SNC-Lavalin/Genivar consortium, PowerPoint presentation of the Impact Study on the Tadoussac bridge, Hôtel Le Manoir, Baie-Comeau, June 2009, p. 19. / see the La Boule bridge project of the same study, which has the same characteristics and price as the one proposed near the ferries. (Addendum 1 of the 2009 impact study)
  3. SNC-Lavalin/Genivar consortium, Impact Study on the Tadoussac bridge (2009). Technical Feasibility component, Budget estimate, Deck without sidewalk, pages 1-29 and 1-30
  4. COWI Engineering, letter of August 18, 2015 to the President of the Société du Pont sur le Saguenay, Ms. Micheline Anctil.

The costs of the proposed roads

Plan of the Saguenay bridge project near Tadoussac with cost estimates (2015)

Finally, for those wondering about the costs of the access infrastructure to these bridges, let us mention that:

The logic of a highway bridge (4 lanes) led the SNC 2009 consortium to plan an equivalent highway access on both (2) shores of the Saguenay.

Yet the construction criteria for a highway are very different from those for a 2-lane road such as Route 138. E.g.: less pronounced curves and grades, resulting, among other things, in a dozen imposing highway viaducts spread over 5.5 kilometres. A single one of these highway viaducts stretches 1.4 kilometres, i.e. the length of the bridge itself, etc.

Estimated costs of the access roads, SNC 2009 project: ± $500M (2015 $). (See the 2009 Impact Study of the SNC-Lavalin/Genivar consortium, Addendum 1, pages 5 and 10)

For its part, the structure proposed by SPS 2015 is paired with the construction of access roads meeting the design criteria of a 2-lane national highway like the current Route 138 at the Saguenay River, with a 600-metre tunnel. (See the Bridge Project table above.)

Estimated costs of the access roads and the tunnel (also appendix E30, para. 2) of the SPS 2015 project: ± $250M. (2015 $)

In summary, in 2015 dollars

Total cost of the SNC 2009 project: Bridge: $900M + Roads: $500M = Total: $1.4 billion

Total cost of the SPS 2015 project: Bridge: $300M + Roads: $250M = Total: $550 million

Additional information:

Total cost of the ferries and onshore infrastructure (wharves, garages, buildings, etc.)

  • 2 versatile vessels: $350M
  • Expected lifespan: 45 years, after a major mid-life refit at 20 years.
  • Adjustments to wharves and access ramps: $75M
  • Pre-boarding area at the bottom of the Tadoussac hill, requested by the STQ: $50M and more
  • Bypass of Baie-Sainte-Catherine and passing lanes to dissolve exit platoons, Tadoussac hill and upgrading of the Tadoussac wharf (to be planned): roughly $150M

Total: $625M and more, plus recurring annual operating costs of $20M/year (average operating costs of the last 3 years according to the STQ annual report). These amounts do not include the costs related to the new, more massive and complex ferries, nor those related to the collision of November 21, 2019 between the ferry and the Baie-Sainte-Catherine wharf.

Not only will a bridge at La Boule cost less than the ferries, but it will also eliminate recurring annual operating costs.

In terms of the use of public funds, all the information corroborates the conclusions established nearly 50 years ago in the 1973 and 1976 studies by Mr. Thomas Monti, PhD, Eng. , Harvard graduate in administration and economist, to the effect that a bridge will cost taxpayers less than maintaining the ferries at Tadoussac. One must of course also consider all the nuisances the ferries cause for the road and maritime safety of Route 138 users, the economic development of the region, the survival of belugas and other marine mammals, the unpredictability of travel times and the deterrent effects on exchanges between the region and the rest of the continent, etc. (See the case for the bridge on the front page of this site).

No one at the Société du Pont claims to have great experience in the construction of such bridges. That is why we did not hesitate to go and meet those who hold the expertise at the international level. Of course, the access-road projects, like the bridge itself, can be optimized, and that is precisely why a Project Office was set up at the Ministry of Transport. It is obviously in the best interest of Québec taxpayers that the figures we have be validated and refined. Since everything indicates that a bridge is clearly advantageous for taxpayers, it is imperative that the Project Office be able to issue the calls for tenders to update the studies and undertake the work preliminary to construction as soon as the government has validated these figures. The person in charge at the office of the Minister of Transport has already acknowledged the seriousness and credibility of the figures put forward for the SPS 2015 project.

The Québec government can and must quickly prioritize the project to open up the region. It is the only way to plan a reasonable use of public funds while opening the door to the last isolated province of Canada, as the Government of Canada wishes: Newfoundland and Labrador (Radio-Canada article, January 7, 2020). It is time to move forward and give the region a basic and essential tool for its development: a completed and safe road, from one end to the other.