A bridge at Tadoussac, affordable and advantageous!

Published on

by

in

, ,
pontslider

Dear members of the Société du Pont,

For 15 years now, the Société du Pont sur le Saguenay à Tadoussac has been working to facilitate the construction of a bridge at Tadoussac. Since then, there has been no shortage of twists and turns: the Charbonneau Commission, the announcement of new ferries, the construction of bridges similar to the Tadoussac one for a fraction of the proposed costs. Engineering firms have examined the project, each with different objectives and solutions sometimes far-fetched, sometimes realistic. Through this renewed site, we wish to explain why the solution presented by two engineering firms in 2009 is not viable and does not represent a solution suited to the need, and we present the solution judged optimal by the experts of the 1979 and 1986 studies and by us. By comparing the realistic costs of the new bridge, we found that it is more advantageous for the Québec government to build the bridge and its approaches and maintain them than to maintain at Tadoussac a 24-hour-a-day ferry service with crews, risks and inherent costs.

Annual savings of at least $10M would lighten the direct contribution of Quebecers to open the road to the Côte-Nord region and the neighbouring province.

Millions for studies

Pont LGL carte des tracés D (1979)
LGL bridge, map of alignments D (1979)

The Société has therefore worked over the past few years to carry out a complete review of the studies proposed between 1973 and 2015. Nearly 40 years of prevarication, of promising projects sometimes contradicted by counter-studies carried out internally at the MTQ. We dwelt on a study commissioned in 1979 by the Minister of Transport under René Lévesque, Mr. Lucien Lessard. This study, after analyzing various options, proposed a bridge on alignment D upstream of the Hydro-Québec power lines at the place known as La Boule on the Sacré-Cœur side and downstream of Caye à David on the Baie-Sainte-Catherine side. This study was enriched by a feasibility analysis and a cost assessment for building the approach roads on both sides (excerpt from the 1979 study). We then reviewed a second study prepared by the architect Pierre Brisset in 1986, which also located the bridge in the same sector.

Logical approaches, since it is the narrowest and most practical place to build a bridge at a reasonable cost at the mouth of the Saguenay. There are already roads to reach the sites on both sides.

Bridge options
Naturam-Génivar Study 1999

A new study in 1999, known as the opportunity study, proposed an alignment near the crossing (P4) that had been raised in a MTQ counter-study in 1979 (Lévesque et al.) following the one commissioned by Minister Lucien Lessard — a counter-study of which the Minister himself was never made aware. The 1999 study thus set aside all the alignments upstream of the crossing (P1, P2, P3) (Cost analysis of the 1999 study) by “tunnelling” significant segments of the access roads to the bridges, thereby substantially increasing the costs of these options, even though one of them, upstream of the lines (P1), had de facto been considered the most economical since 1979. This tunnelling approach is one of the elements at the origin of the dead end into which the opportunity study led the subsequent 2009 impact study.

Options de ponts: Étude Naturem-Génivar 1999
Bridge options: Naturam-Génivar Study 1999

The suspension-bridge expert firm retained to design the bridge (Buckland and Taylor) received a request only to assess the alignment near the ferries, since it was presented only with options P3, P4, P5, of which P3 and P5 were already known to be undesirable from the earlier studies.

After preparing a project at site P4 near the crossing, the B&T experts recommended lowering the level of the deck above the water to below 80 m, whereas the project was planned at 88 m, in order to substantially reduce the costs of the bridge (recommendation of Buckland and Taylor). The engineers of the 2009 study would ignore this recommendation.

In 2001, an impact study costing $2M was commissioned from the SNC-Lavalin and Génivar consortium by the Côte-Nord regional office of the Québec Ministry of Transport (MTQ) (Project notice, Ministry of Transport 2002). Unfortunately, a few months after the announcement of the study, its initiators were transferred to other regions and a new director general from Montréal, unfamiliar with the realities of the region, became responsible for the study for 2 years, after which the MTQ regional management was changed a few more times. These many changes had the effect of preventing rigorous management of the project and thus led to the emergence of a disproportionate project to overcome the obstacles of a poorly chosen alignment. This study contradicts the recommendation of the experts of the previous 1999 study,

Simulation pont SNCLavallin

Buckland and Taylor, to lower the clearance of the deck above the water from 88 m to less than 80 m. It proposes a bridge whose deck will be sloped and whose clearance will vary between 112 m and 140 m, accompanied by a 900 m viaduct 70 m above the Anse-à-l’Eau lake. By passing over the mountains of Baie-Sainte-Catherine to eliminate a 1.2 km tunnel planned in the 1999 study, the engineers increased the height of the deck and consequently the costs on an ill-suited alignment. As a result, they presented a 3 km-long structure (a raised and sloping suspension bridge of 2.1 km and a 900 m viaduct 70 m above the Anse-à-l’Eau lake, 25 m wide) whose costs, in 2015, would far exceed one billion dollars. At the Société du Pont, we concluded that this project, by its gigantic dimensions, its costs and its location, is not defensible in a context of budgetary restraint, of sensitivity to an internationally renowned historic and tourist site, and above all considering the new technologies and the earlier studies that have defined, for nearly 50 years now, the optimal location. Moreover, several pieces of information transmitted by La Société des Traversiers du Québec to the authors of the 2009 study proved to be erroneous, others were omitted, and as a result they distorted the conclusions. The same applies to the cost-benefit analysis (vessel replacement costs, ferry operating costs and the costs of upgrading the wharves and ferry access infrastructure). It is possible, with the help of firms with the necessary expertise in long suspension bridges, to build a bridge with all the necessary qualities for a fraction of the price proposed in the latest study.

We therefore propose a bridge located at the optimal site: the shortest span, a lower clearance, new tensile properties of the load-bearing cables, greater longevity and a deck width suited to a two-lane national highway such as Route 138.

The time of contradictory and incomplete studies

In fact, we consider that the time for studies on the Tadoussac bridge is over; the project we present, which is essentially a revival of the projects proposed in 1979 and 1986 by the experts, requires a technical update of the LGL 1979 study by a firm specializing in the construction of long suspension bridges. Some of these firms already have offices in Canada. We also suggest that specialized international firms be invited to bid without restrictions so as to build the best possible bridge at the best cost — even if it means buying the rights to reproduce existing bridges whose costs we know, with the necessary adaptations.

Traffic

traffic-sign-6617_640

After discussions with regular users of the crossing and with those “deterred” by the numerous disruptions and the foreseeable and unforeseeable interruptions of the ferry service, we found that the ferry service has for decades been the weak link, the limiting factor to an improvement in traffic and hence to the development and transformation of the North Shore economy from an (Ex-Ex) Extraction and Shipping zone to a zone of extraction, processing and shipping of our resources. We have therefore chosen not to review the many traffic analyses over the years that seek to establish a trend when the ferry service is not up to the task and will not be in the future, thus deterring the establishment of industries in the region. Already, those who have made the courageous choice to process the resource locally are less competitive on the markets because of the uncertainties and delays related to transport by ferry to their extra-regional customers… Even by replacing the 3 summer vessels crossing every 13.5 minutes, with a combined capacity of 220 vehicles (75, 75 and 70), with 2 new vessels of 220-vehicle capacity (110, 110), which will no longer be able to cross every 13.5 minutes given the foreseeable loading and unloading times for 110 vehicles, the problem will remain entirely — and moreover, the harm to road safety and traffic flow will increase unless the MTQ, particularly in the Capitale-Nationale region, agrees to invest significant sums to adapt the road to the dissolution of the future mega-platoons of 110 vehicles that will take to the road as they leave the boats. The road’s capacity is saturated at the Saguenay crossing, and multiplying analyses of traffic variations in this context is futile.

Road safety, the ferry syndrome and the mega-platoons to come

Already in 2005, Route 138 on the Côte-Nord, and particularly the fifty or so kilometres on either side of the ferries, was ranked the most dangerous in Québec. The description of the ferry syndrome by the coroner Dr. Arnaud Samson partly explains why (Dr. Samson’s report). In this context of roads that do not sufficiently allow passing near the Saguenay, how can the current platoons be dissolved on an unsuitable road?

More than 60% of two-lane national highways like Route 138 on the Côte-Nord allow passing, either via an additional passing lane or on dashed lines.

Between Baie-Sainte-Catherine and Saint-Siméon, for example, over 37 km passing is possible on only 10% of the distance, and then between Saint-Siméon and La Malbaie this percentage is 19%, still far from the 60% average on two-lane national highways in Québec. Yet on Québec’s national highways, how many segments are hit by sudden waves of 75 vehicles disembarking from boats to cross a village on either side at reduced speed and then travel dozens of kilometres trapped in platoons on a substandard road — in grades, curves and particularly in the ratio of passing zones?

An important question, still unanswered.

If today we cannot dissolve platoons of 50 vehicles within more than 20 kilometres (excerpt from the 2004 study on platoons), what actions will the MTQ have to take when platoons of 110 vehicles form at the exit of the large boats that the Société des Traversiers wishes to put in service by April 2016?

A solution known for nearly 50 years, affordable and effective:

The bridge at La Boule

The construction of a bridge at the place known as La Boule, upstream of the Hydro-Québec cable crossing, meets the requirements and the experts’ recommendations.

The alignment

Carte du nouvelle emplacement

Map of the new location

The bridge at La Boule (P1)

New technologies make it possible to build a bridge with a 200-year lifespan at a reasonable cost (see the Hardanger Bridge and the Narvik bridge in Norway).
A more advantageous solution than maintaining a ferry service. Annual and growing savings are foreseeable. The 2 ferries under construction will be versatile and able to operate at the STQ’s other crossings. A fixed bridge at $250M, or two ferries that to date cost $200M and will not be delivered before 2017. A simple choice, knowing that the bridge will be functional for 200 years if the European standards in force are applied, that it will be paid for over the first 40 years and that afterwards only maintenance costs will remain. Maintaining the ferries means maintaining 5 crews day and night on each boat, fuel costs and maintenance costs. Each ferry must be modernized at great expense after 20 years and has a lifespan of 40 years, after which it must be replaced.

Building a bridge will allow a reallocation of the funds paid to the Société des Traversiers to the payment of the bridge, and a sum roughly assessed at $16M annually will return to the state’s coffers. (See the 2015 study)

VuePont
Detailed map of the La Boule site
Sketch of the proposed suspension bridge at La Boule
Map of the alignment options studied

The advantages

  • Lower costs: a project of $400M (2015) in total including the approach roads, rather than the $1,400M (2015) proposed in 2009 by SNC-Lavalin/Génivar.
  • Road safety: an end to platoons, traffic routed around the villages of Baie-Sainte-Catherine and Tadoussac.
  • Fluidity: an end to the unpredictable trips related to the crossing — time lost, navigation risks, breakdowns, strikes, deterrence, detours, etc.
  • Tourism: the possibility of harmoniously developing the tourism potential on both sides of the mouth of the Saguenay, in particular a reconfiguration of tourism activity around the Anse-à-l’Eau lake in Tadoussac and on the Route 138 hill towards the current ferries.
  • Tourism potential of Pointe-Noire and of whale-watching cruises to be developed without the drawbacks of tourism coexisting with heavy traffic.
  • Proximity of a future expressway alignment to free up the coastal tourist roads and facilitate the movement of heavy vehicles and through traffic while reducing the time required (map of the future alignment).
  • Improved accessibility of the economic hub of eastern HCN, Sacré-Cœur-sur-le-Fjord, thus facilitating its industrial and tourism development.
AB: SNC 13km, LGL 24km Différentiel 11km ou 7 minutes

AB: SNC 13 km, LGL 24 km — difference 11 km or 7 minutes

The challenges

The travel time between the junction of Route 172 with Route 138 and the Rivière aux Canards bridge at Baie-Sainte-Catherine will be lengthened by 7 minutes compared with the 2009 option (12 km vs 23 km).

Mitigation measures to counter the possible effects of job losses on the ferries, although it is expected that jobs will be required for the maintenance of the bridge and that attrition and relocation measures for employees can be put in place during the years of plan preparation and construction.

Comparing ourselves

We then set about assessing comparable projects around the world.

In Korea, China, Turkey and elsewhere, long suspension bridges like the one needed at Tadoussac have been built or are currently under construction. We focused on similar bridges built in Scandinavia, at latitudes higher than Québec’s, where winters are harsh. Norwegian expertise in this field is particularly recognized.

Following our analyses, we concluded that the option presented in 1979 by the LGL engineers and the one presented in 1986 by the architect Brisset are in fact the best option, with a proposal to build a bridge with a main span of 1,150 m instead of the 1,310 m of the 2009 study, a deck clearance above the water of 70 m instead of the 112 to 140 m of the 2009 project, a deck width of 15 m instead of the 25 m proposed, etc.

We therefore wanted to compare the obvious best option — a bridge with the shortest span at La Boule, upstream of the power lines — with similar projects in Scandinavia.

  • The Hardanger Bridge, Norway: built between 2009 and 2013. This bridge, with a main span of 1.31 km, is similar to the project presented in 2009 on the alignment near the ferries, which has a main span of 1.35 km. (identify each of the 3 bridges with a photo of the structure, the deck and other details if needed.)
tableauHardanger
  • The Hålogaland Bridge, Norway: construction 2014 to 2017. This shorter bridge, 1.14 km, is similar to the bridge project at La Boule, 1.15 km.
  • The Höga Kusten Bridge, Sweden, 1997. This bridge, 17.8 m wide, carries a 4-lane highway.
Hardanger Bridge (Norway), a suspension bridge comparable to the one proposed at Tadoussac
Höga Kusten Bridge (Sweden) seen from above
Höga Kusten Bridge, Sweden (photo Sven Wusch, CC BY-SA 2.0)
Hålogaland Bridge, Narvik, Norway

We have also included the latest project proposed in the 2009 impact study and a comparative table of the various bridges according to different parameters that partly explain the cost differences between the projects.

tabcomparaison

It can be seen that the costs of the project proposed in 2009 by the SNC-Lavalin and Génivar consortium exceed the costs of similar bridges in Scandinavia by 356%. Several very conservative technical choices and anomalies in the calculations (insert article: Hydro-Québec sues Dessau and Génivar) and in the process leading to the choice of alignment explain this difference. Moreover, in Scandinavia, governments have experts in supervising such projects and can therefore oversee the work and control costs.
The costs indicated concern the construction of the bridge only, without considering the cost of the approach roads, tunnels and viaducts, which can vary considerably according to the topography of the terrain. Of course, these costs are the result of international calls for tenders and reflect healthy international competition rather than the environment with the appearance of collusion and corruption described by the Charbonneau Commission. Steel and concrete are the two main components of a modern suspension bridge. (Insert the article concerning Hydro-Québec and the steel suppliers.)
Finally, the La Boule project we propose could be built in 4 years, like the Narvik, Hardanger and Höga Kusten bridges, rather than the project presented in 2009 near the ferries, which required 9 years of construction. We have added the Île d’Orléans bridge to the table to indicate carriageway lanes of 3.1 m in width each. This bridge will be rebuilt within a few years.

Taxiarchos228 at the German language Wikipedia [GFDL (https:::www.gnu.org:copyleft:fdl.html) or CC-BY-SA-3.0 (https:::creativecommons.org:licenses:by-sa:3.0:)], via Wikimedia Commons

Photo of the Île d’Orléans bridge by Taxiarchos228 at the German language Wikipedia

New technologies

The width of the carriageway lanes and of the deck, longevity through dehumidification of the load-bearing cables, the increased tensile properties of the main load-bearing cables, and the dehumidification of these same cables are all factors that make it possible to reduce total costs while optimizing the longevity and efficiency of the new bridge.

The MTQ has indicated that a bridge with 2 lanes plus 1 service lane for pedestrians, bicycles, snowmobiles, etc. meets the needs for linking Route 138 at Tadoussac. However, the 2009 project suggested a 4-lane bridge because, at the time, Canadian engineers were not familiar with the new technologies that now allow the construction of long 3-lane suspension bridges (a 15 m-wide deck instead of the 25 m proposed in 2009). On a bridge with a total span of 2 km as proposed in 2009, a 15 m deck instead of 25 m substantially lowers costs: less steel, less weight, less massive piers, lighter cables, etc.

Finally, the dehumidification of the load-bearing cables and of their anchorage chambers now makes it possible to plan for lifespans of 200 years and more for a suspension bridge by eliminating corrosion.

In short, a bridge built at Tadoussac with international expertise in long suspension bridges represents a cost of about $250M, to which must be added $50M for the construction of a 600 m tunnel under the La Boule mountain and $100M for a new road between the Route 138–Route 172 junction and the entrance to the Rivière aux Canards bridge. The cost of the bridge is carried over from the cost of the recent bridges on the Hardanger fjord and near the town of Narvik. The cost of the tunnel is calculated according to international standards, and the cost of the road is that of similar roads built near the site on Route 138 in rocky and mountainous terrain, i.e. $5M/km.

So a bridge and its approaches would cost $400M. (add ferry vs. bridge comparison 24 vs 32 ??)


graphCoutpont

Yes, but what will become of the new ferries that are to be delivered in April 2016?

During a meeting between the member for Saguenay, the president of the Société du Pont and the president of La Société des Traversiers du Québec (STQ), this question was raised. The president of the STQ assured us that the new ferries would be versatile and able to operate at all the Société’s crossings, and that therefore the construction of new ferries would not hinder the eventual construction of a bridge, since they can replace ferries currently at the end of their useful life elsewhere. Moreover, considering the increased harm to road safety that can be foreseen with waves of 110 vehicles invading a road unsuited to dissolving such platoons for lack of adequate passing zones, we consider that it would be more advantageous for the public treasury and for the safety of users to keep the current ferries in place until the bridge is built, since they allow more flexibility in the schedules for an identical total capacity (A. Imbeau 75 veh. – J. Deschênes 75 veh. – F.-A. Savard: 70 veh.), total 220 spaces. They will be replaced by 2 boats of 110 spaces each: total 220 vehicles. The ferry wharves could be used for tourism purposes and free up the wharves of Tadoussac and Baie-Sainte-Catherine to facilitate better tourism development.

Conclusion

An assessment of the costs of maintaining the ferry service of around $32M/year, to which the amortization costs of the road works to adapt the approach road segments of the crossing to the platoons formed at the exit must be added.
Compared with the capital costs of the roads and the new bridge and its maintenance, i.e. $24M annually, this explains the importance of reviewing how the Côte-Nord and Labrador are served. The use of public funds will be optimized by building a bridge at a fair price in the optimal location.

After analyzing the bridge options presented by the successive studies over 45 years, the most economical and environmentally respectful solution is the one proposed by the study of the LGL engineers (Letendre, Girouard, Lalonde) in 1979 at the request of the Minister of Transport of the day. A tunnel of about 600 m would be needed on the left bank, with access grades on both sides not exceeding 6% and 4-lane roads to facilitate the coexistence of passenger vehicles and tractor-trailers on the approach road segments to the bridge.

We therefore ask the Québec government to update the optimal alignment proposed in the LGL study — an alignment set aside by the authors of the 1999 Opportunity Study for inexplicable reasons. This alignment still appears to us today to be the best.